New bridge installed in UK over busy rail line

Work to install a new bridge for the UK’s busiest rail freight line has been carried out over the A160 at the Port of Immingham. The project forms part of the Port of Immingham Improvement Scheme, a €118.15 million (£88.4 million) series of works being carried out on behalf of Highways England. The project involves upgrading 5km of the A160 from single carriageway to dual carriageway, and constructing a number of new structures. Because of the volume of rail traffic using the stretch of track, the new bridg
January 12, 2016 Read time: 2 mins
Work to install a new bridge for the UK’s busiest rail freight line has been carried out over the A160 at the Port of Immingham. The project forms part of the Port of Immingham Improvement Scheme, a €118.15 million (£88.4 million) series of works being carried out on behalf of 8100 Highways England. The project involves upgrading 5km of the A160 from single carriageway to dual carriageway, and constructing a number of new structures. Because of the volume of rail traffic using the stretch of track, the new bridge had to be installed within a tight 76 hour window.

The engineering team included Costain Engineering Services and specialist contractors such as Walters, Freyssinet , Trackwork and SPI Appleton. In order for the installation to be completed within the designated time, the team had to carry out extensive planning beforehand.

The bridge weighed in at just under 4000tonnes and was slid into place using the Autofoncage method, which utilises four large strand jacks. These jacks push the bridge as they pull against the resistance of the strands, which are fixed into the guide raft and a thrust wall.

The team used 3D and 4D Building Information Modelling which allowed them to visualise, plan and share every piece of information with the wider team, clients and stakeholders. In addition to the 4D modelling, the team also completed a Quantative Schedule Risk Assessment, which helped to identify key areas which needed special attention.

No major civil engineering project comes without its challenges and for this project the stability of the old rail embankment caused the biggest hurdle by extending the period the team needed to carefully backfill the structure. The team overcame this challenge and worked closely with Network Rail to manage the completion of the works within the allocated time.

As well as carrying the country’s busiest freight railway line, the new bridge will allow the new highway link to pass underneath it.

For more information on companies in this article

Related Content

  • Closer ties with Highways England Collaborative Delivery Framework
    April 13, 2017
    Highways England is reconsidering its procurement to encourage innovation and ultimately deliver more for less. Kristina Smith spoke to client, contractors and material suppliers to find out more. A group of senior managers is being addressed by a local resident who lives close to some proposed road works. The resident is angry, persistent and quite rude. The question is: how will these managers respond?
  • Foiled by foliage from Biotecture
    June 27, 2022
    Richard Sabin, managing director of Biotecture*, details how living walls provide an innovative solution for reducing air pollution and improve air quality along congested urban highways.
  • Superlative formwork’s global appeal
    April 25, 2013
    The latest formwork solutions are enabling some tough bridge-building projects to be delivered in South America and Europe, while the world’s largest construction equipment show is seeing the merits of other cutting-edge formwork. Guy Woodford reports. Taking a road and rail link across one of South America’s largest rivers, together with its swamps and floodplain, calls for a new crossing of superlative dimensions. Two 135.5m pylons for the third bridge across the Orinoco River in Venezuela are taking shap
  • Minister gives green light for UK road schemes
    May 8, 2012
    Roads Minister Mike Penning yesterday gave the green light for development work to be carried out on six new major UK road schemes. The development work, which will take place over the next three years, aims to prime the road schemes for completion in the early years of the next spending review period (post 2015). The six proposed road schemes, which aim to boost economic growth as part of the Government’s National Infrastructure Plan, are: