The Nepalese authorities are now addressing structural problems on a series of important bridge links in the country

Major structural problems have been identified in several bridges in Nepal.
March 1, 2012 Read time: 2 mins
Major structural problems have been identified in several bridges in Nepal. Construction work on seven large bridges in Nepal has been halted due to the problems arising in the pier construction.

Work has been stopped on bridges located at Ghurmi and carrying the Udayapur-Okhaldhunga road over the Sunkoshi River and at Khurkot carrying the Sindhuli-Manthali road over the Sunkoshi River. Work has also halted on a bridge in West Nepal carrying the Chnichu-Jajarkot road over the Bheri River, on the Tawa River bridge, the Siwai bridge, the Tadi bridge at Nuwakot and on the bridge over the Junga River at Dhanusa.

A bridge expert in Nepal says that due to geological conditions in Nepal, pier construction faces problems. The expert suggests that bridges with piers should be avoided in the country and that arched structures, though more expensive to build, are more suitable for the country's rugged terrain and would offer long term cost benefits through reduced maintenance needs.

Pier problems at the Bheri Bridge have resulted in it being replaced by a suspension bridge and this has been suggested as another suitable bridge design solution for the country. The issue is endemic, with the country's geology and geography playing a key role. Bridge scour is a serious problem in Nepal, due to the country's mountainous terrain, deep rock valleys and fast flowing rivers. 2664 Nepal's Department of Roads has issue a notice that a further seven bridges are in a serious condition and require repairs.

Bridges requiring repair are at Mugling carrying the Prithvi Highway, the Marsyangdi Bridge carrying the Aanbukhaireni-Gorkha road, the Seti bridge carrying the Khaireni-Bhimad road, the Jharahi bridge carrying the Mahendra highway and the Kaligandaki bridge carrying the Siddhartha highway. The other structures are the Bheri bridge carrying the Ratna highway, the Tamakoshi bridge carrying the Lamosanghu road, the Sunkoshi bridge carrying the Lamosanghu - Jiri road and the Tadi bridge carrying the Pasanglamhu road.

For more information on companies in this article

Related Content

  • Concrete highway linking Mexico with US
    March 17, 2016
    A new concrete surface has been constructed along the busy Monterrey-Nuevo Laredo highway in Mexico. This route is of prime importance both for Mexico and its neighbour, the US, as it is the main export-import route between the two countries. Located in northeast Mexico, the Monterrey-Nuevo Laredo highway connects Mexico with the state of Texas in the United States. The route carries 52% of Mexico’s imports and exports and is crucial to the country’s economy, as well as for that of the US. CEMEX Mexic
  • The US FAST Act: a job left unfinished
    April 4, 2016
    US roads and bridges are crumbling at an alarming rate as state governments wring their hands over the increasingly scarce money for repairs. Enter the FAST Act. But is it enough? US state transportation department officials, as well as highway contractors and operators, breathed a sigh of relief in December. For months the highways infrastructure sector waited anxiously to see where the necessary money for road projects would come from. For several years, the Highways Trust Fund – the usual way of paying f
  • Tasmanian bridge proposal faces controversy
    October 27, 2020
    The design proposal for a new Tasmanian bridge project faces controversy.
  • Formwork innovations help bridge building
    July 7, 2015
    A series of formwork developments are helping with challenging bridge construction projects around the world - Mike Woof writes In the Polish city of Krakow, a cost-effective cable stayed bridge is being constructed using a balanced cantilever technique. The current expansion of the Krakow metropolitan railway network (KST) requires the building of a crossing of the Krakow-Plaszow railway junction. Ensuring that daily rail operations remained unaffected during the construction of the 252m long crossing w