Montreal’s new Champlain Bridge is in a race against time

Montreal’s US$3.24 billion Champlain Bridge across the St Lawrence River may not be open on time, according to a report by the independent Auditor General. The 3.4km cable-stayed bridge has two decks supporting three lanes of highway traffic in each direction. A third, central deck supports a mass transit system and a multi-use path. The new bridge will replace the nearby 50-year-old Champlain Bridge which has been deteriorating at an alarming rate. The government signed a contract in 2015 with a private
June 8, 2018 Read time: 2 mins
Touch and go for Montreal’s Champlain Bridge (photo: courtesy Signature on the St Lawrence - December 2016)

Montreal’s US$3.24 billion Champlain Bridge across the St Lawrence River may not be open on time, according to a report by the independent Auditor General.

The 3.4km cable-stayed bridge has two decks supporting three lanes of highway traffic in each direction. A third, central deck supports a mass transit system and a multi-use path.

The new bridge will replace the nearby 50-year-old Champlain Bridge which has been deteriorating at an alarming rate.

The government signed a contract in 2015 with a private partner, Signature on the Saint Lawrence Group led by Canada-based SNC-Lavalin Group, to deliver the project for just under $3 billion, excluding the government’s project management and land acquisition costs. The contract called for the new bridge to be ready for use by 1 December, according to the Auditor General’s report.

It included a 42-month construction period and a 30-year operation and maintenance period. Other sections of the project were scheduled to come into use by 31 October 2019.

Among the criticisms made by Auditor General was the federal government’s slow decision to invest in a new bridge instead of maintaining the existing one.

“This matters because the delay in decision making entailed avoidable expenditures of more than [$385 million], apart from the economic costs to the greater Montréal area due to the congestion and load limitations on the existing bridge,” the report says.

The report also criticised government’s Infrastructure Canada department for completing its analysis of procurement models for the project two years after it announced the choice of a public-private partnership model.

“If the department had thoroughly analysed the procurement models for the project, it would have found that the public-private partnership could be more expensive than a traditional model.”

The Auditor General of Canada conducts independent audits of federal government projects and operations. It reports to the House of Commons of Canada, not to the government. The audits provide members of Parliament with objective information to help them examine the government's activities and hold it to account.

Related Content

  • Rebuilding a historic bridge linking the US and Canada
    March 8, 2016
    While many road authorities in North America are finding it difficult to stretch their bridge assets beyond half a century, one bridge is closing in on its centenary - David Arminas reports The international Peace Bridge, connecting the Canadian province of Ontario with the US state of New York, is 88 years young this year, and still going strong.
  • East End Crossing Project—Availability payment P3 in action
    July 14, 2017
    Indiana exercised its authority to use a P3 contract when it partnered with Kentucky for new bridges across the Ohio River. Barney Allison and John Smolen* explain the groundbreaking availability payment deal. Earlier this year, traffic began rolling over the new tolled Lewis and Clark Bridge spanning the Ohio River from northern Kentucky to southern Indiana. The cable-stayed bridge is part of the award-winning Ohio Bridges Project to untangle traffic within the greater metropolitan area of Louisville, Kent
  • The Lessons of the Genoa bridge collapse
    April 23, 2019
    The partial collapse of the Polcevera viaduct, better known as the Morandi Bridge, has prompted debate regarding the technical and administrative aspects of maintaining road infrastructures. We discussed it with the engineer Gabriele Camomilla, former Director of Research and Maintenance of the Società Autostrade, who coordinated the only major structural intervention performed on the bridge, carried out in the early 1990s
  • COWI wins Massey Tunnel design contract
    February 18, 2022
    COWI will develop an eight-lane immersed tunnel for the George Massey Crossing Project near Vancouver, Canada.