Mersey Gateway Project reaches half-way point across the Mersey

The Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey. Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon. When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes. “We’re now more than 50
March 10, 2017 Read time: 2 mins
The 6126 Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey.

Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon.
 
When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes.
 
“We’re now more than 50% through this highly visual phase of the Mersey Gateway construction,” said Gareth Stuart, project director of the Merseylink construction joint venture. “People will be able to see the stay cables connected to the bridge deck as it emerges across the river week by week.”
 
Each stay cable consists of up to 91 steel strands that sit inside a stay pipe – the outer casing that provides protection from weathering. More than 1,300km of the strands will be used on the project.

Every single strand needs to be installed individually, explained Merseylink’s design manager, George Moir. “It’s gone well so far, and we’re installing around six stays per week from the three pylons. The first two strands are threaded through the stay pipe then the tower crane lifts the pipe up to the anchor point in the upper pylon where the top ends of the strands are fixed into place.
 
“The bottom ends of the strands are then attached to the anchor point in the bridge deck and stressed using a hydraulic system. This enables us to get the correct level of tension needed to support that segment of bridge deck,” said Moir. “We then use a winch system through the stay pipe to winch the remaining strands up one by one. Once all of the strands have been installed they sit in parallel inside the stay pipe to form the stay cable.”
 
The stay cables vary in length; with the shortest measuring approximately 41m and the longest measuring 226m.

For more information on companies in this article

Related Content

  • Peri’s formwork and shoring solution for the “East End Crossing”
    July 6, 2016
    Pylons almost 90m high are a striking feature of a new cable-stayed East End Crossing bridge over the Ohio River in Louisville, Kentucky state in the US The pylons are characterised by their complex shapes and massive legs and cross beams. Peri provided a comprehensive overall concept for its construction – consisting of a planning solution with perfectly matched formwork, climbing, shoring and scaffolding systems along with extensive on-site support. With a Peri solution, the construction crew were a
  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo
  • Riga's newest bridge improved traffic flow
    April 11, 2012
    An alliance of companies has come together to realise major infrastructure projects in Latvia including its biggest bridge. Patrick Smith reports. Riga, the Latvian capital, has the finest collection of Art Nouveau buildings in Europe and its centre is on the UNESCO World Heritage List.
  • Riga's newest bridge improved traffic flow
    May 9, 2012
    An alliance of companies has come together to realise major infrastructure projects in Latvia including its biggest bridge. Patrick Smith reports. Riga, the Latvian capital, has the finest collection of Art Nouveau buildings in Europe and its centre is on the UNESCO World Heritage List. The city of some 750,000 people (the country's total population is 2.2 million) is bounded to the south by Lithuania and to the north by Estonia, and is the second largest in Baltic States. To the east is Russia and Belarus.