Mersey Gateway Project reaches half-way point across the Mersey

The Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey. Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon. When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes. “We’re now more than 50
March 10, 2017 Read time: 2 mins
The 6126 Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey.

Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon.
 
When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes.
 
“We’re now more than 50% through this highly visual phase of the Mersey Gateway construction,” said Gareth Stuart, project director of the Merseylink construction joint venture. “People will be able to see the stay cables connected to the bridge deck as it emerges across the river week by week.”
 
Each stay cable consists of up to 91 steel strands that sit inside a stay pipe – the outer casing that provides protection from weathering. More than 1,300km of the strands will be used on the project.

Every single strand needs to be installed individually, explained Merseylink’s design manager, George Moir. “It’s gone well so far, and we’re installing around six stays per week from the three pylons. The first two strands are threaded through the stay pipe then the tower crane lifts the pipe up to the anchor point in the upper pylon where the top ends of the strands are fixed into place.
 
“The bottom ends of the strands are then attached to the anchor point in the bridge deck and stressed using a hydraulic system. This enables us to get the correct level of tension needed to support that segment of bridge deck,” said Moir. “We then use a winch system through the stay pipe to winch the remaining strands up one by one. Once all of the strands have been installed they sit in parallel inside the stay pipe to form the stay cable.”
 
The stay cables vary in length; with the shortest measuring approximately 41m and the longest measuring 226m.

For more information on companies in this article

Related Content

  • Tensar’s Glasstex makes the grade in UK’s Smart Motorway upgrade
    February 27, 2017
    A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.
  • New safety barrier solutions protect road users
    February 21, 2012
    Novel safety barrier solutions are coming to market, writes Mike Woof The safety barrier market is a focus for innovative products designed to meet a range of different applications. The diverse range of vehicle types on the road poses numerous technical challenges to barrier manufacturers. At the same time, different applications such as motorcycle safety, end treatments, bridge barriers and roadside obstacle protection require novel solutions. Although motorcycles account for only a small proportion of ve
  • Efficient aggregate production with new technology
    December 9, 2022
    New equipment is providing major benefits for aggregate production, offering superior product quality as well as increased throughput, while also being able to better meet sustainability targets for customers
  • Beyond cost: forging a solutions-led partnership for highways carbon-saving
    December 30, 2024
    Changing highways procurement is increasingly focusing material specification to drive carbon savings as well as cost. A longstanding partnership between Huyton Asphalt and Tarmac is delivering new solutions for highways clients in the UK.