Mersey Gateway Project reaches half-way point across the Mersey

The Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey. Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon. When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes. “We’re now more than 50
March 10, 2017 Read time: 2 mins
The 6126 Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey.

Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon.
 
When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes.
 
“We’re now more than 50% through this highly visual phase of the Mersey Gateway construction,” said Gareth Stuart, project director of the Merseylink construction joint venture. “People will be able to see the stay cables connected to the bridge deck as it emerges across the river week by week.”
 
Each stay cable consists of up to 91 steel strands that sit inside a stay pipe – the outer casing that provides protection from weathering. More than 1,300km of the strands will be used on the project.

Every single strand needs to be installed individually, explained Merseylink’s design manager, George Moir. “It’s gone well so far, and we’re installing around six stays per week from the three pylons. The first two strands are threaded through the stay pipe then the tower crane lifts the pipe up to the anchor point in the upper pylon where the top ends of the strands are fixed into place.
 
“The bottom ends of the strands are then attached to the anchor point in the bridge deck and stressed using a hydraulic system. This enables us to get the correct level of tension needed to support that segment of bridge deck,” said Moir. “We then use a winch system through the stay pipe to winch the remaining strands up one by one. Once all of the strands have been installed they sit in parallel inside the stay pipe to form the stay cable.”
 
The stay cables vary in length; with the shortest measuring approximately 41m and the longest measuring 226m.

For more information on companies in this article

Related Content

  • Pilosio’s an MP tower of strength
    July 1, 2013
    Pilosio has supplied a set of 18 MP high-capacity towers for the construction of a viaduct on the Bellinzona-Lugano section of the new trans-Alpine railway, due for completion by the end of 2014. The viaduct is divided into five sectors of varying distances, from 110m for the first to 100 for the second. Both were due to be completed this month. The third and fourth sectors will be 90m long, while the fifth will span 45m – forming a flyover across Strada Cantonale, which links Locarno and Bellinzona.
  • Three consortia to make final bids for Gordie Howe International Bridge
    January 25, 2016
    The Windsor-Detroit Bridge Authority has chosen three final bidders for the six-lane Gordie Howe International Bridge to be built between the Canadian city of Windsor and Detroit in the US state of Michigan. The estimated US$2 billion toll bridge, to be built under a public private partnership, is expected to be finished by 2020.
  • Terex Washing Systems displays great 4Site at bauma 2016
    April 15, 2016
    Terex Washing Systems (TWS) is this week staging the official launch of its 4Site project management service – part of the company’s ongoing commitment to serve customer’s needs. There are three different project management service packages available – Silver, Gold and Platinum – with each including four key steps. Appraise sees TWS carry out a full appraisal of a customer’s project needs, giving them accurate and timely guidance and technical advice. Plan involves a comprehensive project plan tailored t
  • Bridge surface repair improves safety
    July 9, 2012
    Modern products are making life easier for those who have to look after bridges in need of repair Aproject to repair a bridge in the American state of Tennessee has brought safety benefits and improved the ride quality for drivers using the crossing. The Chickasaw Bridge spans the Ellington Parkway and it has benefited from a rehabilitation job by contractor Jamieson Construction. The roadway on the bridge was in a poor state and required frequent patching, and to tackle the problem, the Tennessee DOT consi