Mersey Gateway Bridge project progress

Work is well in hand on the Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high. A specialist automatic climbing system is being used to construct the
October 6, 2016 Read time: 2 mins
The Mersey Gateway Bridge project in the UK has reached a major milestone in its construction
Work is well in hand on the 6126 Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high.

A specialist automatic climbing system is being used to construct the bridge pylons. This equipment builds one vertical 5m section at a time. It then repeatedly climbs upwards to create the next section until the structure is complete. Construction teams have completed 30 sections for the south pylon and 27 for the north pylon. In all, 21 sections will be built for the central pylon. A total of 2,230m3 of concrete was poured for the south pylon, and 1,890m3 for the north pylon.

Gareth Stuart, project director at Merseylink, said, “Hitting the highest point on the project is a significant milestone and it’s a testament to the tenacity and expertise of our construction crews who have worked extremely hard, often in challenging conditions, to get the job done. We’ll be holding a special site celebration to thank all of the teams involved.”

The next phase of work involves installing steel stay cables to connect the three bridge pylons to the main bridge deck. This will begin in the next couple of weeks. Halton’s six-lane river crossing is on schedule to open in autumn 2017.

For more information on companies in this article

Related Content

  • Russia's key highway development project
    May 28, 2012
    One of the largest construction programmes in Europe is being carried out to get a Russian resort ready for the Winter Olympics. Patrick Smith reports. Daytime temperatures top 30°C in September, and with hundreds of shops and hotels, it is not difficult to see why Sochi has become Russia's premier holiday playground. The city, on the east coast of the Black Sea, near the border with Georgia, bustles with tourists, and this is boosted with delegates at the 9th International Investment Forum Sochi 2010.
  • VIDEO: Sarens raises the pylon for New Wear Crossing in Sunderland
    February 13, 2017
    It was as weekend working in Sunderland city, northeast England, for global lifting specialist 8569 Sarens.

    Over the two days, the Belgian company gently raised a 1,550tonne steel pylon that will form the backbone of the New Wear Crossing – no official name yet – across the River Wear.

    General work on the two-span cable-stay bridge started on the bridge in May 2015. The structure will be supported by the single double pylon and will have four vehicle lanes, as well as dedicated cycle and pedestrian routes.
  • Zoomlion’s advanced lifting and concrete pumping technology
    October 14, 2013
    Zoomlion is a world leader in concrete pumping and lifting technology, with an array of highly sophisticated solutions – Mike Woof reports. Compared with other global manufacturers of construction machines, Zoomlion is a comparatively new entrant to the market as the firm is just over 20 years old. However, Zoomlion is now recognised as a world leader in the lifting and concrete pumping markets, developing innovative machines that push the boundaries of technology. The company has grown both organically and
  • Multiple asphalt plants supply major highway construction
    July 12, 2012
    One company has produced eight asphalt plants for a major project, and others are introducing new models as Patrick Smith reports Algeria's US$11.2 billion East-West Highway development, the world's largest current highway construction project, forms part of the larger Trans-Maghreb Motorway project, and is scheduled for completion in 2010. It will run for 1,216km, ensuring the link between Annaba in the north-east and Tlemcen in the north-west, passing directly through 24 provinces and linking Algeria to T