Mersey Gateway Bridge project progress

Work is well in hand on the Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high. A specialist automatic climbing system is being used to construct the
October 6, 2016 Read time: 2 mins
The Mersey Gateway Bridge project in the UK has reached a major milestone in its construction
Work is well in hand on the 6126 Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high.

A specialist automatic climbing system is being used to construct the bridge pylons. This equipment builds one vertical 5m section at a time. It then repeatedly climbs upwards to create the next section until the structure is complete. Construction teams have completed 30 sections for the south pylon and 27 for the north pylon. In all, 21 sections will be built for the central pylon. A total of 2,230m3 of concrete was poured for the south pylon, and 1,890m3 for the north pylon.

Gareth Stuart, project director at Merseylink, said, “Hitting the highest point on the project is a significant milestone and it’s a testament to the tenacity and expertise of our construction crews who have worked extremely hard, often in challenging conditions, to get the job done. We’ll be holding a special site celebration to thank all of the teams involved.”

The next phase of work involves installing steel stay cables to connect the three bridge pylons to the main bridge deck. This will begin in the next couple of weeks. Halton’s six-lane river crossing is on schedule to open in autumn 2017.

For more information on companies in this article

Related Content

  • Italian highway bridge and tunnel link
    February 21, 2022
    A major Italian highway bridge and tunnel link is under construction.
  • Doka feels the heat in Qatar orbital highway project
    September 19, 2019
    The FIFA World Cup 2022 in Qatar is getting closer so completing major infrastructure projects on time has been a priority for the government. The Gulf state is also in the midst of its Qatar National Vision 2030, launched in 2008 with the aim to "transform Qatar into an advanced society capable of achieving sustainable development" by 2030. Improving infrastructure will help the country of just under 3 million people attain greater social and economic levels, according to the government. Finishing critic
  • Low-entry Mercedes-Benz Econic has high visibility
    June 4, 2019
    Mercedes-Benz says that it’s low-entry Econic truck has been awarded the maximum safety-specific five-star Direct Vision rating by Transport for London. Utilities contractor Ferns Surfacing has just invested in a pair of 32tonne Mercedes-Benz Econic trucks decked out as tipper-grabs and is operating them on surface reinstatement and resurfacing duties in and around London. Ferns has 10 depots across south-east England and East Anglia, north-east of London. With its deep, panoramic windscreen and full-heig
  • Looking ahead for Power Curbers
    September 26, 2023
    Power Curbers president Stephen Bullock discussed business trends with Mike Woof