Mersey Gateway Bridge project progress

Work is well in hand on the Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high. A specialist automatic climbing system is being used to construct the
October 6, 2016 Read time: 2 mins
The Mersey Gateway Bridge project in the UK has reached a major milestone in its construction
Work is well in hand on the 6126 Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high.

A specialist automatic climbing system is being used to construct the bridge pylons. This equipment builds one vertical 5m section at a time. It then repeatedly climbs upwards to create the next section until the structure is complete. Construction teams have completed 30 sections for the south pylon and 27 for the north pylon. In all, 21 sections will be built for the central pylon. A total of 2,230m3 of concrete was poured for the south pylon, and 1,890m3 for the north pylon.

Gareth Stuart, project director at Merseylink, said, “Hitting the highest point on the project is a significant milestone and it’s a testament to the tenacity and expertise of our construction crews who have worked extremely hard, often in challenging conditions, to get the job done. We’ll be holding a special site celebration to thank all of the teams involved.”

The next phase of work involves installing steel stay cables to connect the three bridge pylons to the main bridge deck. This will begin in the next couple of weeks. Halton’s six-lane river crossing is on schedule to open in autumn 2017.

For more information on companies in this article

Related Content

  • LagoonHull project put on hold
    February 8, 2023
    The plan by the UK city of Kingston upon Hull is to transform the city centre and river frontage running from the 2.2km-long, single-span suspension Humber Bridge.
  • Italy road tunnel project excavated
    July 9, 2018
    Italy’s A3 Highway is being upgraded, which will improve transport between Salerno and Calabria. Upgrading Italy’s A3 highway is of prime importance for developing the south of the country and is a project that has been prioritised for construction. The A3 Salerno-Reggio-Calabria highway is a non-toll road managed by ANAS, Italy’s state-owned company that constructs and maintains highways. The route runs a total of 443km, with the road having originally been built between 1966 and 1974. However, the origina
  • Estonia surveys major roads with a RetroTek-M retroreflectometer
    May 22, 2019
    During the past two years, Estonia’s Road Administration has clocked up 4,021km during a retroreflectivity project on all main state roads and on basic roads. Estonia’s Road Traffic Development Department of the Estonian Road Administration has been working with ERC Consulting to gather retroreflectivity data on road markings on all main state roads and basic roads. The work has shown that out of 1,609km of main state roads, 20% had problems. The reflective effect is created by glass beads on the surf
  • Scotland’s Queensferry Crossing opens to traffic
    August 30, 2017
    The new Queensferry Crossing in Scotland is now open to traffic, with the first vehicles crossing at 2am this morning. The landmark design has set precedents in engineering, its three 207m high towers making it the tallest of its type in the UK and at 2.7km, also the longest three tower cable-stayed bridge built anywhere in the world. The bridge has a design life of 150 years and features two traffic lanes in either direction, as well as emergency lanes on either side. The new bridge will help reduce the ch