Mersey Gateway Bridge project progress

Work is well in hand on the Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high. A specialist automatic climbing system is being used to construct the
October 6, 2016 Read time: 2 mins
The Mersey Gateway Bridge project in the UK has reached a major milestone in its construction
Work is well in hand on the 6126 Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high.

A specialist automatic climbing system is being used to construct the bridge pylons. This equipment builds one vertical 5m section at a time. It then repeatedly climbs upwards to create the next section until the structure is complete. Construction teams have completed 30 sections for the south pylon and 27 for the north pylon. In all, 21 sections will be built for the central pylon. A total of 2,230m3 of concrete was poured for the south pylon, and 1,890m3 for the north pylon.

Gareth Stuart, project director at Merseylink, said, “Hitting the highest point on the project is a significant milestone and it’s a testament to the tenacity and expertise of our construction crews who have worked extremely hard, often in challenging conditions, to get the job done. We’ll be holding a special site celebration to thank all of the teams involved.”

The next phase of work involves installing steel stay cables to connect the three bridge pylons to the main bridge deck. This will begin in the next couple of weeks. Halton’s six-lane river crossing is on schedule to open in autumn 2017.

For more information on companies in this article

Related Content

  • UK: Work starts on Mersey Gateway main bridge deck
    June 2, 2016
    Work has started on 2.2km Mersey Gateway’s main bridge deck as the project enters its third year of construction. The new six-lane toll bridge will link the English towns of Runcorn and Widnes and teams will begin to connect the steel support cables to the deck and upper pylons this summer. Trinity, the project’s movable scaffolding system (MSS), has cast the first 250m of the north approach viaduct and a new MSS is on its way to Halton to build the south approach viaduct. The local road network is al
  • First concrete beam raised for new Mersey bridge link
    December 11, 2015
    The first concrete bridge beam for a junction on the new Mersey Gateway route has been lifted into place. Work is underway on a major road junction for the Mersey Gateway Project, with the first of 156 of the concrete beams has been lifted into place as work ramps up at a major road junction. A 550tonne capacity crane lowered the 106tonne beam into position at the Bridgewater junction in Runcorn, where the new Astmoor Bridgewater viaduct is being built over the Bridgewater canal. Two elevated slip roads ar
  • Emovis continues with Mersey Gateway tolling
    March 18, 2022
    Emovis provides collection of tolls and charges for both Mersey Gateway Crossing and the older 87m-long Silver Jubilee Bridge through its merseyflow brand name.
  • First deck span completed for Mersey Gateway's north approach viaduct
    April 4, 2016
    The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of tra