Legal battle for Croatia’s Peljeski Bridge contract continues

Only days after Croatia rejected initial complaints, contractors Astaldi, Ictas and Strabag said that they will submit new complaints over the Peljeski bridge winning bid. Croatian media report that Turkey's Ictas, Italy's Astaldi and the Austrian company Strabag are planning to submit a new complaint to the Croatian High Court against a decision by the state procurement authority DKOM to reject their previous complaints. At issue is the awarding of the Peljeski bridge and access roads project to the
April 19, 2018 Read time: 3 mins

Only days after Croatia rejected initial complaints, contractors Astaldi, Ictas and Strabag said that they will submit new complaints over the Peljeski bridge winning bid.

Croatian media report that Turkey's Ictas, Italy's Astaldi and the Austrian company Strabag are planning to submit a new complaint to the Croatian High Court against a decision by the state procurement authority DKOM to reject their previous complaints.

At issue is the awarding of the Peljeski bridge and access roads project to the China Road and Bridge Corporation (CRBC).

Daily newspaper Jutarnji List wrote that Astaldi and Ictas will submit complaints separately. Meanwhile, Strabag will request temporary measures that will prevent the signing of contract agreement between the Croatian roads company Hrvatske Ceste and the CRBC.

Media suggest that if the High Court decides there is a basis for the complaints, project works could be delayed by a further four months up to two years. In that case, financial support for the bridge could be jeopardised.

Bids for construction of the four-lane 2.4km bridge were submitted in the middle of last year. The bridge will connect Croatian territory by traversing the Adriatic Sea’s Mali Ston Bay. Vehicles must currently head from Croatia into Bosnia to re-enter a peninsula that is Croatian territory.

The Turkish and Italian consortium tendered bids around €343 million Strabag offered around €349 million. But China Road and Bridges Corporation came in at around €208 million.

Last month DKOM said there were no grounds for retendering the contract. DKOM said there was no violation of procurement rules by the successful bidder, China Road and Bridge, and that no issues related to the bidding price.

DKOM also noted that any issues over bidders submitting unsustainably low prices in order to win work was an issue for the European Commission that handle complaints over dumping pricing.

While the bridge will be good for the economy of the Croatian area, Bosnia and Herzegovina has in the past requested that Croatia pause procurement for the project pending discussions between the two countries over the design.

Bosnia’s concern is that the largest ocean-going ships should have access up Ston Bay to Bosnia’s only sea port, Neum, should the Bosnian government decide to upgrade the terminals there.

Discussions have resulted in Croatia accepting design changes – and added costs - suggested by Bosnia, including an increase of bridge's height from 35m to 55m and spacing bridge supports at least 200m apart.

Project completion was originally set for 2022.

In June, the European Commission approved €357 million of the European Union’s Cohesion Policy funds to build the bridge – around 85% of the project’s cost. The European Union is also funding supporting infrastructure, such as access roads, including tunnels, bridges and viaducts, the building of an 8km bypass near the town of Ston and upgrading works on the existing road D414.

Related Content

  • Norway mega-project contract for Fugro
    December 20, 2017
    The largest road project in Norway’s history has seen Fugro win a second major contract from the Norwegian Public Roads Administration (NPRA). The work on the E39 Coastal Highway is for the construction of a 1,100km route from Kristiansand in the south to Trondheim in central Norway. This project is expected cost around €34.4 billion (NOK 340 billion).
  • Bulgaria continues with Struma motorway, Blagoevgrad to Krupnik
    September 14, 2017
    Bulgaria has started work on a 12.6km section of Struma motorway between the southwestern towns of Blagoevgrad and Krupnik. A consortium led by Bulgarian construction company Agromah is building the section under a contract worth just over €71 million, according to the regional development ministry.
  • Norway drops planned fixed link between Moss and Horten
    October 25, 2018
    Norway’s Road Administration has stopped investigations into a proposed bridge or tunnel spanning 10.5km of the Oslofjord between Moss and Horten, according to Norwegian media. The Ministry of Transport has ordered Veivesendet to cancel consultations amid the government’s growing concern over the cost of any fixed link across the narrows, around 65km south of the capital Oslo. The half-hour car-ferry crossing as part of National Highway 19 will continue as usual. Several thousand people and vehicles m
  • Contract for Romanian highway construction signed
    May 10, 2012
    In Romania the road authorities have signed a deal for the construction of a 22km stretch of highway in a contract worth €91 million. The Portuguese contractor Monte Adriano will construct the section linking Nadlac with Pecica. Romania has pledged to improve and expand its highway network with the construction of new links, and much of the funding for its highway plans has been provided by the European Bank for Reconstruction and Development and the European Investment Bank (EIB).