Legal battle for Croatia’s Peljeski Bridge contract continues

Only days after Croatia rejected initial complaints, contractors Astaldi, Ictas and Strabag said that they will submit new complaints over the Peljeski bridge winning bid. Croatian media report that Turkey's Ictas, Italy's Astaldi and the Austrian company Strabag are planning to submit a new complaint to the Croatian High Court against a decision by the state procurement authority DKOM to reject their previous complaints. At issue is the awarding of the Peljeski bridge and access roads project to the
April 19, 2018 Read time: 3 mins

Only days after Croatia rejected initial complaints, contractors Astaldi, Ictas and Strabag said that they will submit new complaints over the Peljeski bridge winning bid.

Croatian media report that Turkey's Ictas, Italy's Astaldi and the Austrian company Strabag are planning to submit a new complaint to the Croatian High Court against a decision by the state procurement authority DKOM to reject their previous complaints.

At issue is the awarding of the Peljeski bridge and access roads project to the China Road and Bridge Corporation (CRBC).

Daily newspaper Jutarnji List wrote that Astaldi and Ictas will submit complaints separately. Meanwhile, Strabag will request temporary measures that will prevent the signing of contract agreement between the Croatian roads company Hrvatske Ceste and the CRBC.

Media suggest that if the High Court decides there is a basis for the complaints, project works could be delayed by a further four months up to two years. In that case, financial support for the bridge could be jeopardised.

Bids for construction of the four-lane 2.4km bridge were submitted in the middle of last year. The bridge will connect Croatian territory by traversing the Adriatic Sea’s Mali Ston Bay. Vehicles must currently head from Croatia into Bosnia to re-enter a peninsula that is Croatian territory.

The Turkish and Italian consortium tendered bids around €343 million Strabag offered around €349 million. But China Road and Bridges Corporation came in at around €208 million.

Last month DKOM said there were no grounds for retendering the contract. DKOM said there was no violation of procurement rules by the successful bidder, China Road and Bridge, and that no issues related to the bidding price.

DKOM also noted that any issues over bidders submitting unsustainably low prices in order to win work was an issue for the European Commission that handle complaints over dumping pricing.

While the bridge will be good for the economy of the Croatian area, Bosnia and Herzegovina has in the past requested that Croatia pause procurement for the project pending discussions between the two countries over the design.

Bosnia’s concern is that the largest ocean-going ships should have access up Ston Bay to Bosnia’s only sea port, Neum, should the Bosnian government decide to upgrade the terminals there.

Discussions have resulted in Croatia accepting design changes – and added costs - suggested by Bosnia, including an increase of bridge's height from 35m to 55m and spacing bridge supports at least 200m apart.

Project completion was originally set for 2022.

In June, the European Commission approved €357 million of the European Union’s Cohesion Policy funds to build the bridge – around 85% of the project’s cost. The European Union is also funding supporting infrastructure, such as access roads, including tunnels, bridges and viaducts, the building of an 8km bypass near the town of Ston and upgrading works on the existing road D414.

Related Content

  • Albania prequalifying for bypasses around Vlore and Fier
    October 5, 2017
    Albania is pre-qualifying contractors for two major bypass projects, according to the European Bank for Reconstruction and Development. One is for construction of a 29km bypass of the southern Adriatic port city of Vlore with work expected to take 27 months. Vlore, with a population or around 130,000, is the country’s third largest city.
  • Tunnel contract for Bosnian highway
    December 17, 2012
    Turkish company Cengiz Insaat has reportedly been awarded the €115 million contract for the construction of the Suhodol-Tarcin motorway in Bosnia. The works, which will be done in cooperation with Bosnian company Euroasfalt, will include two tunnels. One of them will be 400m long, while the other will be 2.5km. Works are expected to be completed by 2014. Meanwhile, bids are now being offered for a major highway project in Bosnia. This follows the opening of the tender process for the project by Bosnian high
  • German court decides for Fehmarnbelt
    November 18, 2020
    Danish state-owned company Femern is responsible for the 18km road-rail tunnel.
  • Spain’s A21 motorway gets €182m of financial help
    September 22, 2017
    Autovía del Pirineo has secured €182 million for the construction and operation of several sections of the A21 motorway in Spain’s northern Navarre region. Autovía del Pirineo is a subsidiary of Iridium Concesiones de Infraestructuras and a member of the ACS Group. International law firm Watson Farley & Williams said that it had advised a syndicate of banks and other European institutional funders on the procurement of senior debt facilities worth €182 million for Pirineo.