Legal battle for Croatia’s Peljeski Bridge contract continues

Only days after Croatia rejected initial complaints, contractors Astaldi, Ictas and Strabag said that they will submit new complaints over the Peljeski bridge winning bid. Croatian media report that Turkey's Ictas, Italy's Astaldi and the Austrian company Strabag are planning to submit a new complaint to the Croatian High Court against a decision by the state procurement authority DKOM to reject their previous complaints. At issue is the awarding of the Peljeski bridge and access roads project to the
April 19, 2018 Read time: 3 mins

Only days after Croatia rejected initial complaints, contractors Astaldi, Ictas and Strabag said that they will submit new complaints over the Peljeski bridge winning bid.

Croatian media report that Turkey's Ictas, Italy's Astaldi and the Austrian company Strabag are planning to submit a new complaint to the Croatian High Court against a decision by the state procurement authority DKOM to reject their previous complaints.

At issue is the awarding of the Peljeski bridge and access roads project to the China Road and Bridge Corporation (CRBC).

Daily newspaper Jutarnji List wrote that Astaldi and Ictas will submit complaints separately. Meanwhile, Strabag will request temporary measures that will prevent the signing of contract agreement between the Croatian roads company Hrvatske Ceste and the CRBC.

Media suggest that if the High Court decides there is a basis for the complaints, project works could be delayed by a further four months up to two years. In that case, financial support for the bridge could be jeopardised.

Bids for construction of the four-lane 2.4km bridge were submitted in the middle of last year. The bridge will connect Croatian territory by traversing the Adriatic Sea’s Mali Ston Bay. Vehicles must currently head from Croatia into Bosnia to re-enter a peninsula that is Croatian territory.

The Turkish and Italian consortium tendered bids around €343 million Strabag offered around €349 million. But China Road and Bridges Corporation came in at around €208 million.

Last month DKOM said there were no grounds for retendering the contract. DKOM said there was no violation of procurement rules by the successful bidder, China Road and Bridge, and that no issues related to the bidding price.

DKOM also noted that any issues over bidders submitting unsustainably low prices in order to win work was an issue for the European Commission that handle complaints over dumping pricing.

While the bridge will be good for the economy of the Croatian area, Bosnia and Herzegovina has in the past requested that Croatia pause procurement for the project pending discussions between the two countries over the design.

Bosnia’s concern is that the largest ocean-going ships should have access up Ston Bay to Bosnia’s only sea port, Neum, should the Bosnian government decide to upgrade the terminals there.

Discussions have resulted in Croatia accepting design changes – and added costs - suggested by Bosnia, including an increase of bridge's height from 35m to 55m and spacing bridge supports at least 200m apart.

Project completion was originally set for 2022.

In June, the European Commission approved €357 million of the European Union’s Cohesion Policy funds to build the bridge – around 85% of the project’s cost. The European Union is also funding supporting infrastructure, such as access roads, including tunnels, bridges and viaducts, the building of an 8km bypass near the town of Ston and upgrading works on the existing road D414.

Related Content

  • How Florida paved the way for availability payments in the US
    November 21, 2014
    New financing models have been used to deliver key transport links in the US - * Patrick D Harder and Brandon J Davis Florida Department of Transportation’s (FDOT) public-private partnership (PPP) programme has made impressive progress, setting precedents for US transportation planning and funding. On March 26th 2014, FDOT opened 16km of new reversible express lanes as part of its US$1.8 billion I-595 Corridor Roadway Improvements Project. Just a few months later, on August 3rd 2014, FDOT opened twin tunnel
  • £185 million deal for A9 in Scotland
    August 9, 2024
    A £185 million deal has been awarded for the A9 in Scotland.
  • North Germany bypass project faces delay
    November 9, 2017
    Construction delays are holding up the opening of a new bypass in northern Germany that will connect the towns of Löhne and Bad Oeynhausen. Construction work on the link commenced in 2008 and has so far cost some €170 million. In all the project is expected to cost €208 million to complete. Although the vast majority of the work has been carried out on the new bypass some finishing works remain to be completed.
  • A decade for completing the 105km Cork-Limerick M20
    December 10, 2018
    It could be a decade before Ireland’s 105km Cork-Limerick M20 motorway is finished, the government has warned. Road safety groups and businesses have been pushing for the €900m M20 motorway because of issues over fatalities on the existing rural route. Simon Coveney, Ireland’s deputy prime minister, said the government was committed to the route – the largest motorway project to be undertaken in the next 25 years, and money has been earmarked for it. According to Irish media, Coveney also noted tha