Skip to main content

JCCBI says US$300m for demolishing Montreal’s old Champlain Bridge

Tearing down the old steel truss cantilever Champlain Bridge in Montreal could cost around US$300 million, according to preliminary estimates by a federal government agency. Also, until the nearby new Champlain Bridge is finished, it will cost US$93 million annually to maintain the old one, according to Jacques Cartier and Champlain Bridges Incorporated (JCCBI), the federal Canadian agency that oversees several major road infrastructure assets in the city. Dismantling will start in 2019 at the earliest and
April 11, 2017 Read time: 2 mins
Tearing down the old steel truss cantilever Champlain Bridge in Montreal could cost around US$300 million, according to preliminary estimates by a federal government agency.

Also, until the nearby new Champlain Bridge is finished, it will cost US$93 million annually to maintain the old one, according to 2880 Jacques Cartier and Champlain Bridges Incorporated (JCCBI), the federal Canadian agency that oversees several major road infrastructure assets in the city.

Dismantling will start in 2019 at the earliest and it will take up to four years, Canadian media reported. JCCBI has said that material from the old bridge will be recycled and used in projects around Montreal.

More than 140,000 cars use it daily, making it one of the busiest single-span bridges in Canada. But years of heavy use of de-icing salt during harsh winters has deteriorated the structure.

Work on a new bridge started in 2016 and it is scheduled to open at the end of 2018.

The 6km Champlain Bridge, opened in 1962, along with approach viaducts is made of prestressed concrete beams supporting a prestressed concrete deck overlaid with paved with asphalt. The total bridge complex is around 14.5km and spans the Saint Lawrence River and Saint Lawrence Seaway, connecting the Montreal boroughs of Verdun and Le Sud-Ouest to Brossard. It is named after the French explorer Samuel de Champlain, who founded Quebec City, the Quebec province’s capital, in 1608.

Together with the Jacques Cartier Bridge, it is administered by JCCBI, a Canadian Crown Corporation which reports to Infrastructure Canada.

For more information on companies in this article

Related Content

  • Champlain Bridge set to open by end of year, says SNC-Lavalin
    May 14, 2018
    The Canadian city’s replacement Champlain Bridge will open on schedule at the end of the year. Montreal, one of Canada’s largest cities, will have a well-earned Christmas present in December when the new Champlain Bridge opens after 42 months of construction. The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, runs from the île des Soeurs to Brossard, immediately dow
  • Champlain Bridge set to open by end of year, says SNC-Lavalin
    March 6, 2018
    The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
  • SSL settles legal issues, Champlain Bridge to open December 21
    April 18, 2018
    Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
  • Canada: work officially starts on Montreal’s Champlain Bridge
    June 25, 2015
    Canada’s infrastructure minister, Denis Label, officially broke ground for Montreal’s replacement Champlain Bridge, saying the project will likely cost US$3.42 billion. The 3.4km Champlain Bridge Corridor Project, including spans and highway expansions, is expected to be completed by 2019. SNC-Lavalin, the 50% stakeholder in the winning consortium Signature on the Saint-Lawrence, recently announced it had finalised the deal with new Champlain Bridge owner Infrastructure Canada. Signature on the Saint-