Independent experts suggest interim Bay Bridge fix

The state Toll Bridge Program Oversight Committee (TBPOC) says it has received a report from the Federal Highway Administration (FHWA) in which the federal agency concludes that installing temporary seismic elements will make the new East Span of the San Francisco-Oakland Bay Bridge safe for traffic, and should be put in place as soon as possible. This FHWA plan involves inserting large steel plates, known as shims, into each of four bearings, improving their ability to safely distribute energy during an ea
August 15, 2013 Read time: 3 mins
The state Toll Bridge Program Oversight Committee (TBPOC) says it has received a report from the 2410 Federal Highway Administration (FHWA) in which the federal agency concludes that installing temporary seismic elements will make the new East Span of the San Francisco-Oakland Bay Bridge safe for traffic, and should be put in place as soon as possible.

This FHWA plan involves inserting large steel plates, known as shims, into each of four bearings, improving their ability to safely distribute energy during an earthquake.

The TBPOC in July asked federal highway officials to analyse the shim installation plan to assess its viability to allow the new East Span to open prior to the permanent retrofit for broken bolts on the easternmost pier of the self-anchored suspension portion of the new bridge. Federal officials recommend adopting that plan. The FHWA proposal is consistent with that of internationally known bridge designers Dr. Peter Taylor of Buckland & Taylor, in North Vancouver, British Columbia, and Dr. John Kulicki of Modjeski and Masters in Mechanicsburg, Pennsylvania, who submitted separate analyses of the shimming strategy originally advocated by the Toll Bridge Seismic Safety Peer Review Panel.

“Safety has always been the driving factor for any decision related to this lifeline bridge, and these reports confirm that the temporary fix could allow us to safely move traffic while work continues on a permanent retrofit,” said Steve Heminger, chairman of the TBPOC. “We will meet in a public session to discuss this important information and to announce the opening date for the Bay Bridge.”

At the July meeting, the TBPOC concluded its investigation into the breakage of a batch of large bolts on the eastern span of the Bay Bridge and recommended that the bridge opening be postponed from the previously announced opening on Labor Day, 2013, until further engineering work could be completed and considered.

The Toll Bridge Oversight Committee was due to hold a public meeting today (15/8) at the MetroCenter Auditorium, in Oakland, during which these reports will be discussed and the opening date for the new East Span announced.

The Toll Bridge Program Oversight Committee was created by the State Legislature in 2005 to provide project oversight and project control for the Toll Bridge Seismic Retrofit Program in California. The TBPOC is comprised of the Director of the Department of Transportation (5246 Caltrans), the Executive Director of the Bay Area Toll Authority (BATA), and the Executive Director of the California Transportation Commission (CTC). The Committee’s oversight and control activities include review and approval of contract bid documents, review and resolution of project issues, evaluation and approval of project change orders and claims, and the issuance of monthly and quarterly programme progress reports.

For more information on companies in this article

Related Content

  • IRF hosts high-level debate on the Belt & Road Initiative (BRI) at ITF Summit 2019
    August 12, 2019
    HE Mehmet Cahit Turhan, minister of Transport and Infrastructure of Turkey, opened with a keynote address at the session on "The Belt & Road: Bridging the gaps for sustainable transport and growth in EurAsia". This was organised by the International Road Federation (IRF) on 22nd May 2019 at the ITF Summit 2019 in Leipzig. The panel included top representatives from the World Bank, BSEC, AIIB, IATA, Michelin and PwC and offered a deep insight into key topics surrounding the BRI. Organised jointly with th
  • IRF’s Marrakech regional event focuses on North Africa
    April 12, 2013
    A series of dynamic meetings in Marrakech signal the forward direction of IRF Geneva as it gears up for a bright new era as a global voice of the road sector. As these pages go to press, IRF Geneva is just emerging from a very rewarding regional conference focusing on North Africa and the Mediterranean that took place from 19-20 March, 2013. The success of this high-level gathering, organised in association with the Moroccan Road Association and Moroccan Motorways (Autoroutes du Maroc), reflects IRF Geneva’
  • US federal highway trust faces running out of cash by 2015
    September 27, 2013
    America’s federal highway trust fund faces running out of money in 2015: a move that will have a “devastating impact” on states that rely heavily on federal funds for their road maintenance and construction needs, transportation officials warned the US Congress this week. Highway contractors, state transportation officials and the U.S. Chamber of Commerce all went to Washington this week to lobby Congress, arguing for a rise in the rate of federal gasoline tax to help boost the coffers.
  • US federal highway trust faces running out of cash by 2015
    September 27, 2013
    America’s federal highway trust fund faces running out of money in 2015: a move that will have a “devastating impact” on states that rely heavily on federal funds for their road maintenance and construction needs, transportation officials warned the US Congress this week. - See more at: http://www.worldhighways.com/sections/general/news/us-federal-highway-trust-faces-running-out-of-cash-by-2015/#sthash.OH7KmQ0C.dpuf