Independent experts suggest interim Bay Bridge fix

The state Toll Bridge Program Oversight Committee (TBPOC) says it has received a report from the Federal Highway Administration (FHWA) in which the federal agency concludes that installing temporary seismic elements will make the new East Span of the San Francisco-Oakland Bay Bridge safe for traffic, and should be put in place as soon as possible. This FHWA plan involves inserting large steel plates, known as shims, into each of four bearings, improving their ability to safely distribute energy during an ea
August 15, 2013 Read time: 3 mins
The state Toll Bridge Program Oversight Committee (TBPOC) says it has received a report from the 2410 Federal Highway Administration (FHWA) in which the federal agency concludes that installing temporary seismic elements will make the new East Span of the San Francisco-Oakland Bay Bridge safe for traffic, and should be put in place as soon as possible.

This FHWA plan involves inserting large steel plates, known as shims, into each of four bearings, improving their ability to safely distribute energy during an earthquake.

The TBPOC in July asked federal highway officials to analyse the shim installation plan to assess its viability to allow the new East Span to open prior to the permanent retrofit for broken bolts on the easternmost pier of the self-anchored suspension portion of the new bridge. Federal officials recommend adopting that plan. The FHWA proposal is consistent with that of internationally known bridge designers Dr. Peter Taylor of Buckland & Taylor, in North Vancouver, British Columbia, and Dr. John Kulicki of Modjeski and Masters in Mechanicsburg, Pennsylvania, who submitted separate analyses of the shimming strategy originally advocated by the Toll Bridge Seismic Safety Peer Review Panel.

“Safety has always been the driving factor for any decision related to this lifeline bridge, and these reports confirm that the temporary fix could allow us to safely move traffic while work continues on a permanent retrofit,” said Steve Heminger, chairman of the TBPOC. “We will meet in a public session to discuss this important information and to announce the opening date for the Bay Bridge.”

At the July meeting, the TBPOC concluded its investigation into the breakage of a batch of large bolts on the eastern span of the Bay Bridge and recommended that the bridge opening be postponed from the previously announced opening on Labor Day, 2013, until further engineering work could be completed and considered.

The Toll Bridge Oversight Committee was due to hold a public meeting today (15/8) at the MetroCenter Auditorium, in Oakland, during which these reports will be discussed and the opening date for the new East Span announced.

The Toll Bridge Program Oversight Committee was created by the State Legislature in 2005 to provide project oversight and project control for the Toll Bridge Seismic Retrofit Program in California. The TBPOC is comprised of the Director of the Department of Transportation (5246 Caltrans), the Executive Director of the Bay Area Toll Authority (BATA), and the Executive Director of the California Transportation Commission (CTC). The Committee’s oversight and control activities include review and approval of contract bid documents, review and resolution of project issues, evaluation and approval of project change orders and claims, and the issuance of monthly and quarterly programme progress reports.

For more information on companies in this article

Related Content

  • East End Crossing Project—Availability payment P3 in action
    July 14, 2017
    Indiana exercised its authority to use a P3 contract when it partnered with Kentucky for new bridges across the Ohio River. Barney Allison and John Smolen* explain the groundbreaking availability payment deal. Earlier this year, traffic began rolling over the new tolled Lewis and Clark Bridge spanning the Ohio River from northern Kentucky to southern Indiana. The cable-stayed bridge is part of the award-winning Ohio Bridges Project to untangle traffic within the greater metropolitan area of Louisville, Kent
  • Simple road safety measures save lives
    February 15, 2012
    Elementary road safety measures quickly pay back the costs of investment and, more importantly, help save lives as Patrick Smith reports. More than 300 people in the UK are alive today or have avoided the prospect of a lifetime of special care because just 15 roads have had simple improvements put in place.
  • Vancouver’s 10-lane bridge replacement for Massey Tunnel remain undecided
    October 23, 2015
    Construction of a 10-lane bridge to replace a congested river tunnel in Vancouver, Canada, is still on target to start in 2017, despite details remaining sketchy.

    The bridge will replace the 60-year-old George Massey Tunnel between the local cities of Richmond and Delta along the provincial Highway 99. But the cost and – importantly – whether it will be a toll bridge have not been declared by the British Columbia provincial government.
  • Recycled pavement use rises again in the US, according to NAPA
    January 16, 2015
    The use of reclaimed asphalt pavement in the United States increased during 2013 after two years of no rise, according the latest report from the US National Asphalt Pavement Association (NAPA). The report found that more than 73 million tons of reclaimed asphalt pavement and 1.7 million tons of reclaimed asphalt roofing shingles were used in new asphalt pavement mixes in the United States during in 2013. Using recycled asphalt material saved about $2 billion in 2013 over the use of virgin materials,