I Lift NY crane places first girder on New York’s Tappan Zee Bridge

One of the world’s largest cranes has placed the first steel girder assembly for the approach span of the new NY Bridge, often called the Tappen Zee Bridge in New York. The barge-mounted I Lift NY super crane with its nearly 100m boom slowly picked up the 125m unit from its delivery barge and gently lowered it onto concrete pedestals in the Hudson River, near the Rockland County side of the bridge. The super crane will install even larger sections of the new bridge, some of which weigh around 907tonne
June 25, 2015 Read time: 3 mins
One of the world’s largest cranes has placed the first steel girder assembly for the approach span of the new NY Bridge, often called the Tappen Zee Bridge in New York.

The barge-mounted I Lift NY super crane with its nearly 100m boom slowly picked up the 125m unit from its delivery barge and gently lowered it onto concrete pedestals in the Hudson River, near the Rockland County side of the bridge.

The super crane will install even larger sections of the new bridge, some of which weigh around 907tonnes, in the coming weeks, according to a statement on the official website of the Tappen Zee Bridge. I Lift NY will also help dismantle the existing 60-year-old structure that was designed to carry up to 100,000 vehicles daily but is now handling about 138,000.

The super crane arrived in the Port of New York and New Jersey in January 2014 after a journey of just under 10,000km from San Francisco Bay, including a tight passage through the Panama Canal in Central America. I Lift NY underwent modifications at a private facility before being moved to the New NY Bridge project site.

The crane is owned by TZC - Tappan Zee Constructors - and is officially registered with the US Coast Guard as the Left Coast Lifter.

The first span of the new twin-span bridge is scheduled to open in 2016 with full opening planned for 2018. The new bridge is designed to last 100 years without major structural maintenance, according to the official bridge website.

It will have eight traffic lanes, four breakdown/emergency lanes, as well as a dedicated commuter bus lane from the day it opens. Designed and constructed to be mass-transit-ready, the new crossing will be able to accommodate bus rapid transit, light rail or commuter rail in the future. The bridge will also include a bike and pedestrian path.

The New NY Bridge project is design-build contract worth $3.9 billion and won by consortium Tappan Zee Constructors. Companies include 6343 Fluor, 1021 American Bridge, Granite, and 1014 Traylor Bros., along with key design firms 2418 HDR, 4121 Buckland & Taylor, URS and GZA.

TZC is working closely on the project with a team of employees from the New York State Thruway Authority and the State Department of Transportation.

For more information on companies in this article

Related Content

  • Bridge engineering worldwide
    July 1, 2013
    Guy Woodford looks at vital bridge construction, repair and inspection projects in China, Europe, North America and Australia The Heron Road Bridge in Ottawa, Ontario in Canada is a vital link within the City’s transport network, as it crosses the Rideau River, which divides the east and west parts of the City. Constructed in 1966-1967, the Heron Road Bridge is approximately 275m long and includes six lanes.
  • New figures reveal world road fatality rates
    February 6, 2015
    Figures now available from the International Road Traffic Accident Database (IRTAD) highlight the risk of travelling by road in some countries. Not all countries compile accurate data from police sources and in many, a high percentage of road traffic crashes go unreported to the authorities. But the data from nations that do compile such information highlights counties where road risks are high and action needs to be taken.
  • US$1.7bn to boost California highway infrastructure
    May 27, 2025
    Projects include rehabilitating roadway and drainage systems and upgrading safety along Interstate 805
  • Panama postpones project for fourth bridge tender
    September 14, 2017
    Panama has postponed the tender process for the fourth bridge crossing over the Panama Canal. This is the fourth time the fourth bridge crossing tender has been postponed. Panama’s Ministry of Public Works (MOP) opted to postpone the tender due to changes in the guidelines. The bridge will have six lanes for motor vehicles as well as twin tracks for metro rail and is expected to cost US$1 billion to construct.