I Lift NY crane places first girder on New York’s Tappan Zee Bridge

One of the world’s largest cranes has placed the first steel girder assembly for the approach span of the new NY Bridge, often called the Tappen Zee Bridge in New York. The barge-mounted I Lift NY super crane with its nearly 100m boom slowly picked up the 125m unit from its delivery barge and gently lowered it onto concrete pedestals in the Hudson River, near the Rockland County side of the bridge. The super crane will install even larger sections of the new bridge, some of which weigh around 907tonne
June 25, 2015 Read time: 3 mins
One of the world’s largest cranes has placed the first steel girder assembly for the approach span of the new NY Bridge, often called the Tappen Zee Bridge in New York.

The barge-mounted I Lift NY super crane with its nearly 100m boom slowly picked up the 125m unit from its delivery barge and gently lowered it onto concrete pedestals in the Hudson River, near the Rockland County side of the bridge.

The super crane will install even larger sections of the new bridge, some of which weigh around 907tonnes, in the coming weeks, according to a statement on the official website of the Tappen Zee Bridge. I Lift NY will also help dismantle the existing 60-year-old structure that was designed to carry up to 100,000 vehicles daily but is now handling about 138,000.

The super crane arrived in the Port of New York and New Jersey in January 2014 after a journey of just under 10,000km from San Francisco Bay, including a tight passage through the Panama Canal in Central America. I Lift NY underwent modifications at a private facility before being moved to the New NY Bridge project site.

The crane is owned by TZC - Tappan Zee Constructors - and is officially registered with the US Coast Guard as the Left Coast Lifter.

The first span of the new twin-span bridge is scheduled to open in 2016 with full opening planned for 2018. The new bridge is designed to last 100 years without major structural maintenance, according to the official bridge website.

It will have eight traffic lanes, four breakdown/emergency lanes, as well as a dedicated commuter bus lane from the day it opens. Designed and constructed to be mass-transit-ready, the new crossing will be able to accommodate bus rapid transit, light rail or commuter rail in the future. The bridge will also include a bike and pedestrian path.

The New NY Bridge project is design-build contract worth $3.9 billion and won by consortium Tappan Zee Constructors. Companies include 6343 Fluor, 1021 American Bridge, Granite, and 1014 Traylor Bros., along with key design firms 2418 HDR, 4121 Buckland & Taylor, URS and GZA.

TZC is working closely on the project with a team of employees from the New York State Thruway Authority and the State Department of Transportation.

For more information on companies in this article

Related Content

  • Algeria bridge lifting with cranes
    January 5, 2017
    Algerian firm SAPTA is currently using four Sennebogen cranes for a bridge project close to Algerian capital Algiers. SAPTA is a specialist in bridge construction and is using the cranes, a combination of crawler and telescopic machines, to lift heavy components weighing up to 60tonnes
  • ARTBA concerned over drop in US highway spending
    March 4, 2013
    Despite the 2012 passage of the US federal surface transportation law, known as MAP-21, the real value of highway and bridge contract awards over the last 12 months was down 3% compared the previous 12 month period. This is according to the latest analysis of McGraw-Hill Dodge data by the American Road & Transportation Builders Association (ARTBA). Taking into account changes in wages, materials and inflation, state and local governments awarded US$54.3 billion in real highway and bridge contract awards bet
  • Russia new programme for developing high-speed roads
    January 14, 2019
    Russia has approved a new state programme for the development of its high-speed road network – Eugene Gerden reports The Russian government has officially approved a new state programme, which is aimed at developing the federal high-speed road network in the country. This programme will run until 2030, according to recent statements by the official state press-service. According to some leading Russian experts in the roadbuilding sector, the need to implement these plans is acute. At present the tota
  • New bridge link needed for Cape Cod
    October 9, 2019
    New bridge links are needed for Cape Cod, in the US state of Massachusetts.