I Lift NY crane places first girder on New York’s Tappan Zee Bridge

One of the world’s largest cranes has placed the first steel girder assembly for the approach span of the new NY Bridge, often called the Tappen Zee Bridge in New York. The barge-mounted I Lift NY super crane with its nearly 100m boom slowly picked up the 125m unit from its delivery barge and gently lowered it onto concrete pedestals in the Hudson River, near the Rockland County side of the bridge. The super crane will install even larger sections of the new bridge, some of which weigh around 907tonne
June 25, 2015 Read time: 3 mins
One of the world’s largest cranes has placed the first steel girder assembly for the approach span of the new NY Bridge, often called the Tappen Zee Bridge in New York.

The barge-mounted I Lift NY super crane with its nearly 100m boom slowly picked up the 125m unit from its delivery barge and gently lowered it onto concrete pedestals in the Hudson River, near the Rockland County side of the bridge.

The super crane will install even larger sections of the new bridge, some of which weigh around 907tonnes, in the coming weeks, according to a statement on the official website of the Tappen Zee Bridge. I Lift NY will also help dismantle the existing 60-year-old structure that was designed to carry up to 100,000 vehicles daily but is now handling about 138,000.

The super crane arrived in the Port of New York and New Jersey in January 2014 after a journey of just under 10,000km from San Francisco Bay, including a tight passage through the Panama Canal in Central America. I Lift NY underwent modifications at a private facility before being moved to the New NY Bridge project site.

The crane is owned by TZC - Tappan Zee Constructors - and is officially registered with the US Coast Guard as the Left Coast Lifter.

The first span of the new twin-span bridge is scheduled to open in 2016 with full opening planned for 2018. The new bridge is designed to last 100 years without major structural maintenance, according to the official bridge website.

It will have eight traffic lanes, four breakdown/emergency lanes, as well as a dedicated commuter bus lane from the day it opens. Designed and constructed to be mass-transit-ready, the new crossing will be able to accommodate bus rapid transit, light rail or commuter rail in the future. The bridge will also include a bike and pedestrian path.

The New NY Bridge project is design-build contract worth $3.9 billion and won by consortium Tappan Zee Constructors. Companies include 6343 Fluor, 1021 American Bridge, Granite, and 1014 Traylor Bros., along with key design firms 2418 HDR, 4121 Buckland & Taylor, URS and GZA.

TZC is working closely on the project with a team of employees from the New York State Thruway Authority and the State Department of Transportation.

For more information on companies in this article

Related Content

  • Rader Hochbrücke construction set for summer
    April 7, 2025
    Work on the Rader Hochbrücke (bridge) near Rendsburg, Germany, will start this summer and take five years, according to DEGES.
  • Customised mill cuts costs
    October 14, 2015
    A special customised cold planer has saved costs and time for a US contractor. In the US, New York State Highway 243 has benefited from an innovative use of novel milling technology. This 17.75km east–west state highway is located in the Southern Tier of New York and has been carrying traffic since the 1930 renumbering of state highways in the state. The NY 243 has been a utilitarian divided highway that begins at an intersection with NY 98 in the town of Freedom and proceeds south-eastward across mostly ru
  • VIDEO: Sarens raises the pylon for New Wear Crossing in Sunderland
    February 13, 2017
    It was as weekend working in Sunderland city, northeast England, for global lifting specialist 8569 Sarens.

    Over the two days, the Belgian company gently raised a 1,550tonne steel pylon that will form the backbone of the New Wear Crossing – no official name yet – across the River Wear.

    General work on the two-span cable-stay bridge started on the bridge in May 2015. The structure will be supported by the single double pylon and will have four vehicle lanes, as well as dedicated cycle and pedestrian routes.
  • Successful resurfacing at New York's JFK Airport
    May 3, 2012
    A huge logistics operation has been carried out successfully at New York's JFK Airport. One of the busiest runways at one of the world's busiest airports is now open to air traffic again, following a 120 day closure for resurfacing.