The project to build the Riederwaldtunnel highway tunnel in Germany is now likely to cost €477 million. The project was originally expected to cost €322 million. The tunnel will stretch 1.1km and will provide a connection between the A66 and A661 routes. Construction work on the tunnel, located near the city of Frankfurt, is expected to commence in 2020.
February 8, 2019 Read time: 1 min

The project to build the Riederwaldtunnel highway tunnel in Germany is now likely to cost €477 million. The project was originally expected to cost €322 million. The tunnel will stretch 1.1km and will provide a connection between the A66 and A661 routes. Construction work on the tunnel, located near the city of Frankfurt, is expected to commence in 2020.

Related Content

  • Progress for Norwegian tunnel project
    September 21, 2018
    Swedish contractor Skanska reports steady progress on its project to construct the Strømnes to Sprova tunnel connection in Norway. The firm has completed the tunnel excavation portion of the work for both the 600m long Holmvik Tunnel and 1,000m long Strømnes Tunnel. The project is costing around €36.5 million and the new road link will measure 5.4km in all, which includes the new tunnels. Work commenced in October 2017 and should be complete in the third quarter of 2019 if all goes to plan. The project is l
  • North Germany bypass project faces delay
    November 9, 2017
    Construction delays are holding up the opening of a new bypass in northern Germany that will connect the towns of Löhne and Bad Oeynhausen. Construction work on the link commenced in 2008 and has so far cost some €170 million. In all the project is expected to cost €208 million to complete. Although the vast majority of the work has been carried out on the new bypass some finishing works remain to be completed.
  • Bosnia Herzogovina highway project receiving EBRD loan
    September 12, 2018
    A loan from the European Bank for Reconstruction and Development (EBRD) worth €180 million will help to pay for the construction of the Corridor Vc highway project. This highway is of key importance for the economic development of Bosnia and Herzegovina as it will provide and improved transport connection with Europe. The loan will help to pay for the construction of three new sections of Corridor Vc, measuring some 16km. The loan will be provided in two tranches, with the first of up to €120 million and b
  • Costs rise for revamping Amsterdam’s IJ and Piet Hein tunnels
    April 18, 2018
    Costs for renovating Amsterdam’s IJ and Piet Hein tunnels are higher than expected, Dutch media report. Renovation of the Piet Hein Tunnel will cost €35 million more than the original €85 million budgeted. However, cost for renovating the IJ Tunnel rose only €3.6 million over the planned more than budgeted €55.1 million. Cost increases are due mainly to upgrading of fire safety systems, according to the media. The 1km-long IJ Tunnel, which opened in 1968, is part of a nearly 1.7km system, including