German highway stretch reopening to be delayed

Repairs to the A20 highway route in northern Germany are now likely to take longer than initially expected. The route will now take until 2023 to repair, with the work costing some €100 million to carry out and requiring a temporary bridge to carry traffic past the failed section. The temporary bridge accounts for more than half of the cost of the work. The geological problems with the A20 Autobahn route first became visible in September 2018 when a section near Tribsees started to suffer from subsidence.
February 19, 2019 Read time: 2 mins
Repairs to the A20 highway route in northern Germany are now likely to take longer than initially expected. The route will now take until 2023 to repair, with the work costing some €100 million to carry out and requiring a temporary bridge to carry traffic past the failed section. The temporary bridge accounts for more than half of the cost of the work.


The geological problems with the A20 Autobahn route first became visible in September 2018 when a section near Tribsees started to suffer from subsidence. This initial subsidence was then followed by a complete collapse of a 40m section of the road and became progressively worse, resulting in a 95m stretch suffering major failure. The presence of peat deposits under the roadway has been blamed for the technical problems. Insufficient stabilisation of the afflicted stretch was carried out prior to building of the road.

Building a road over very soft ground requires special construction techniques. However these methods are well understood, having been developed during the early days of the railway building boom in the UK during the 19th century. The Manchester to Liverpool railway line opened to traffic in 1830 and features a 7.6km stretch built across the Chat Moss bog, with this section of track remaining in use today. Why these techniques were not properly employed for this road project is unclear.

Related Content

  • Czech bridge facing demolition over condition concerns
    October 29, 2018
    A bridge located in Prague, capital of the Czech Republic, is facing calls for its demolition. Concern has been expressed over the condition of the Hlavka Bridge, which spans the Vltava River. The bridge carries heavy vehicle traffic as well as trams and is one of the city’s major transport arteries. It was built originally from 1909 to 1912, replacing an earlier wooden structure. It was then rebuilt so as to cope with vehicle traffic and at present carries up to 100,000 vehicles/day, making it one of the b
  • Saudi Arabian capital Riyadh benefiting from major transport investment
    September 9, 2013
    Saudi Arabia is undergoing a series of upgrades to its transport network in a bid to improve Traffic flow rates and boost safety - Mike Woof reports. The massive growth in the use of motor transport worldwide since the start of the 20th century has transformed every country on the planet. But perhaps no country has changed more dramatically than Saudi Arabia, the world’s leading oil producer. At the start of the 20th century Saudi Arabia’s population was small and the country had few industries while it is
  • Road recycling saves time and costs, reduces emissions
    February 13, 2012
    Stabilisers bring recycling improvements to roads in the UK and Armenia. The local road authorities near the UK city of Bath have saved nearly €250,500 on the cost of repairing a 400m long section of the B3110 Midford Road. This saving has been achieved by opting to recycle and strengthen in-situ the existing surface, instead of using conventional full depth pavement reconstruction.
  • Iterchimica trials more Gipave in Oxfordshire
    November 23, 2023
    Another trial of Iterchimica’s graphene-enhanced Gipave technology gets underway in the English county of of Oxfordshire.