German highway stretch reopening to be delayed

Repairs to the A20 highway route in northern Germany are now likely to take longer than initially expected. The route will now take until 2023 to repair, with the work costing some €100 million to carry out and requiring a temporary bridge to carry traffic past the failed section. The temporary bridge accounts for more than half of the cost of the work. The geological problems with the A20 Autobahn route first became visible in September 2018 when a section near Tribsees started to suffer from subsidence.
February 19, 2019 Read time: 2 mins
Repairs to the A20 highway route in northern Germany are now likely to take longer than initially expected. The route will now take until 2023 to repair, with the work costing some €100 million to carry out and requiring a temporary bridge to carry traffic past the failed section. The temporary bridge accounts for more than half of the cost of the work.


The geological problems with the A20 Autobahn route first became visible in September 2018 when a section near Tribsees started to suffer from subsidence. This initial subsidence was then followed by a complete collapse of a 40m section of the road and became progressively worse, resulting in a 95m stretch suffering major failure. The presence of peat deposits under the roadway has been blamed for the technical problems. Insufficient stabilisation of the afflicted stretch was carried out prior to building of the road.

Building a road over very soft ground requires special construction techniques. However these methods are well understood, having been developed during the early days of the railway building boom in the UK during the 19th century. The Manchester to Liverpool railway line opened to traffic in 1830 and features a 7.6km stretch built across the Chat Moss bog, with this section of track remaining in use today. Why these techniques were not properly employed for this road project is unclear.

Related Content

  • Strabag wins German A3 Autobahn contract
    July 24, 2015
    Austrian contract STRABAG has won the tender process to widen the A3 Autobahn in southern Germany. The contract will see the firm widening the A3 to six lanes in a deal worth €90 million. The A3 connects the cities of Frankfurt and Nuremburg. STRABAG has been awarded the EO 287 contract to widen a 5.7km section of the road using asphalt construction methods in the state of Bavaria. It has also won the EO 259 contract to widen an 8.5km section of road using asphalt construction methods in the state of in Bad
  • US$73 million Francis Scott Bridge replacement contract
    September 3, 2024
    Kiewit has been awarded a US$73 million Francis Scott Bridge replacement contract.
  • New road reduces Carlisle congestion by 20%
    May 11, 2012
    Carlisle, in north-west England, has seen as 20% reduction in congestion since the opening of the city’s US$284million (£176m) Northern Development Route in February this year. Around 10,000 vehicles a day are using the new road, which is broadly in line with the predictions made by highways engineers when building a case to construct a new route connecting the A595 with the M6 around the western flank of the city. Traffic counters positioned on the new road show an average of 9,583 vehicles a day along the
  • Temporary bridge replacement in the US
    July 2, 2019
    A temporary bridge structure provided by Acrow Bridge is maintaining traffic flow for a key crossing in Vermont. The bascule bridge is allowing both vehicular and vessel traffic to pass during the reconstruction work to the North Hero-Grand Isle Drawbridge in Vermont. The US$60 million project involves replacing the historic twin leaf bascule bridge on Lake Champlain. This modular steel bascule bridge is allowing transport to continue to and from the Lake Champlain island towns of North Hero and Grand Isl