German highway stretch reopening to be delayed

Repairs to the A20 highway route in northern Germany are now likely to take longer than initially expected. The route will now take until 2023 to repair, with the work costing some €100 million to carry out and requiring a temporary bridge to carry traffic past the failed section. The temporary bridge accounts for more than half of the cost of the work. The geological problems with the A20 Autobahn route first became visible in September 2018 when a section near Tribsees started to suffer from subsidence.
February 19, 2019 Read time: 2 mins
Repairs to the A20 highway route in northern Germany are now likely to take longer than initially expected. The route will now take until 2023 to repair, with the work costing some €100 million to carry out and requiring a temporary bridge to carry traffic past the failed section. The temporary bridge accounts for more than half of the cost of the work.


The geological problems with the A20 Autobahn route first became visible in September 2018 when a section near Tribsees started to suffer from subsidence. This initial subsidence was then followed by a complete collapse of a 40m section of the road and became progressively worse, resulting in a 95m stretch suffering major failure. The presence of peat deposits under the roadway has been blamed for the technical problems. Insufficient stabilisation of the afflicted stretch was carried out prior to building of the road.

Building a road over very soft ground requires special construction techniques. However these methods are well understood, having been developed during the early days of the railway building boom in the UK during the 19th century. The Manchester to Liverpool railway line opened to traffic in 1830 and features a 7.6km stretch built across the Chat Moss bog, with this section of track remaining in use today. Why these techniques were not properly employed for this road project is unclear.

Related Content

  • The Fehmarnbelt Tunnel, another Danish connection
    June 20, 2017
    The Fehmarnbelt Tunnel between Denmark and Germany is both ambitious and innovative, explains Susanne Kalmar Pedersen, project director at design engineering firm Ramboll, adviser to the client Fehmarn A/S. The ambitious Fehmarnbelt Tunnel - one of Europe’s largest ongoing infrastructure projects - is a priority project within the EU’s Trans European Network (TEN-T) programme. It will link the German island of Fehmarn with the Danish island of Lolland. The tunnel is an 18km immersed combined road and rail l
  • Major project to construct landmark Bay Bridge in California
    October 31, 2012
    Iconic California crossing will offer seismic safety – Adrian Greeman reports A unique single-span single-tower suspension bridge is the iconic centrepiece of a dramatic renewal of the eastern Bay Bridge in California, crossing from San Francisco to Oakland. Tourists in San Francisco sometimes mix up their bridges, identifying as the famous Golden Gate, the double suspension bridge which runs across the wide San Francisco Bay. These serially linked bridges in fact form the Bay Bridge east to Oakland whereas
  • Temporary bridges for Michigan highway works
    September 21, 2023
    Temporary bridges will help with Michigan highway works.
  • Securing safer transportation infrastructure through non-destructive technology
    June 16, 2014
    Kevin Vine reports on the use of non-destructive testing for structural analysis of bridges Seven years ago, the overpass collapse in Laval, Québec that led to the death of five people brought to light severe issues with the state of the country’s bridges and transportation infrastructure. More recently, a crack in the Champlain Bridge to Montreal that forced over 160,000 commuters to find alternate routes to work reaffirmed a need for greater emphasis on early detection before a crisis occurs.