German highway stretch reopening to be delayed

Repairs to the A20 highway route in northern Germany are now likely to take longer than initially expected. The route will now take until 2023 to repair, with the work costing some €100 million to carry out and requiring a temporary bridge to carry traffic past the failed section. The temporary bridge accounts for more than half of the cost of the work. The geological problems with the A20 Autobahn route first became visible in September 2018 when a section near Tribsees started to suffer from subsidence.
February 19, 2019 Read time: 2 mins
Repairs to the A20 highway route in northern Germany are now likely to take longer than initially expected. The route will now take until 2023 to repair, with the work costing some €100 million to carry out and requiring a temporary bridge to carry traffic past the failed section. The temporary bridge accounts for more than half of the cost of the work.


The geological problems with the A20 Autobahn route first became visible in September 2018 when a section near Tribsees started to suffer from subsidence. This initial subsidence was then followed by a complete collapse of a 40m section of the road and became progressively worse, resulting in a 95m stretch suffering major failure. The presence of peat deposits under the roadway has been blamed for the technical problems. Insufficient stabilisation of the afflicted stretch was carried out prior to building of the road.

Building a road over very soft ground requires special construction techniques. However these methods are well understood, having been developed during the early days of the railway building boom in the UK during the 19th century. The Manchester to Liverpool railway line opened to traffic in 1830 and features a 7.6km stretch built across the Chat Moss bog, with this section of track remaining in use today. Why these techniques were not properly employed for this road project is unclear.

Related Content

  • US celebrates road milestone
    February 29, 2012
    The US has celebrated the bicentennial of its first federally funded road.
  • Cost-saving compact twin layer asphalt paving
    February 28, 2012
    Twin-layer paving offers high quality, long lasting road surfaces to be constructed. Paver manufacturer Dynapac is one of the pioneers of the twin-layer paving technique, which it calls Compactasphalt. According to Dynapac this method offers major benefits to contractors and clients alike as roads surfaced using this technique last longer and are cheaper to maintain. To ensure contractors have maximum utilisation of their machines, Dynapac offers a modular paver system that can be operated using the convent
  • Mexico: underwater tunnel in Latin America
    May 8, 2015
    Mexico will benefit from an important new underwater tunnel - Mauro Nogarin writes. The city of Coatzacoalcos is located at the mouth of the river of the same name, in the Gulf of Mexico, 302km from the city of Salina Cruz, Oaxaca, in the east end of trans-isthmian corridor and at the southern end of Veracruz State. The city is seeing a key development as currently construction is 85% completed on the first immersed tube, underwater tunnel in Latin America. The reasons why experts chose this type of tunne
  • Slovakia tunnel sections underway but some delays
    January 23, 2018
    The route for new tunnel links for Slovakia’s D1 highway has been agreed. New tunnels now look set to be built on the 13.5km stretch between Turany and Hubova section of the D1 highway. This plan calls for the construction of the Korbelka and Havran tunnels at an estimated cost of €900 million. Building these two links would bypass the Lower Fatra mountain range, with the Korbelka Tunnel measuring 5.9km and the Havran Tunnel measuring 2.9km long. The Slovak Environment Ministry rejected an appeal against th