German highway stretch reopening to be delayed

Repairs to the A20 highway route in northern Germany are now likely to take longer than initially expected. The route will now take until 2023 to repair, with the work costing some €100 million to carry out and requiring a temporary bridge to carry traffic past the failed section. The temporary bridge accounts for more than half of the cost of the work. The geological problems with the A20 Autobahn route first became visible in September 2018 when a section near Tribsees started to suffer from subsidence.
February 19, 2019 Read time: 2 mins
Repairs to the A20 highway route in northern Germany are now likely to take longer than initially expected. The route will now take until 2023 to repair, with the work costing some €100 million to carry out and requiring a temporary bridge to carry traffic past the failed section. The temporary bridge accounts for more than half of the cost of the work.


The geological problems with the A20 Autobahn route first became visible in September 2018 when a section near Tribsees started to suffer from subsidence. This initial subsidence was then followed by a complete collapse of a 40m section of the road and became progressively worse, resulting in a 95m stretch suffering major failure. The presence of peat deposits under the roadway has been blamed for the technical problems. Insufficient stabilisation of the afflicted stretch was carried out prior to building of the road.

Building a road over very soft ground requires special construction techniques. However these methods are well understood, having been developed during the early days of the railway building boom in the UK during the 19th century. The Manchester to Liverpool railway line opened to traffic in 1830 and features a 7.6km stretch built across the Chat Moss bog, with this section of track remaining in use today. Why these techniques were not properly employed for this road project is unclear.

Related Content

  • Geosynthetics give extra strength to soil reinforcement
    March 14, 2012
    Using geosynthetics for soil reinforcement is highly effective but requires a high quality and trusted geogrid. When it comes to deciding which geogrid is best for a specific project, a number of product parameters must be taken into account. In the design of steep slopes, the most important parameter is the available long term design strength (Pdes). Recently, Colbond has significantly increased this factor for its high performance Enkagrid product, recognised with a newly updated BBA (British Board of Ag
  • Geosynthetics give extra strength to soil reinforcement
    May 3, 2012
    Using geosynthetics for soil reinforcement is highly effective but requires a high quality and trusted geogrid. When it comes to deciding which geogrid is best for a specific project, a number of product parameters must be taken into account. In the design of steep slopes, the most important parameter is the available long term design strength (Pdes). Recently, Colbond has significantly increased this factor for its high performance Enkagrid product, recognised with a newly updated BBA (British Board of Ag
  • Recycling advances from Wirtgen
    June 18, 2012
    German firm Wirtgen is retaining its lead in road recycling technologies – Mike Woof writes Tests on cold recycling with a new layer thickness using Wirtgen's sophisticated WR 4200 machine have shown impressive results according to the firm. The road construction and traffic authority Landesbetrieb Mobilität (LBM) Cochem-Koblenz commissioned a pilot project as part of its plan to optimise the cold in-place recycling process (CIR). The aim was to examine the extent to which the layer thickness can be reduced
  • Scotland’s new Queensferry Crossing over the Forth Estuary
    December 23, 2015
    The new Queensferry Crossing under construction in Scotland will be the third landmark bridge spanning the Forth Estuary - Mike Woof writes When the new Queensferry Crossing over the Forth Estuary opens at the end of 2016, it will be the third landmark bridge to be built spanning this short stretch of water. Lying alongside the existing road bridge and the historic rail bridge, this new structure will be as groundbreaking as the two earlier crossings were at the time of their construction.