Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • The cost of crashes in the US
    May 25, 2023
    The financial cost of road crashes in the US places a heavy burden
  • Colombia’s high bridge construction completion
    June 8, 2018
    Completion of construction work on Colombia Hisgaura Bridge will be achieved in July 2018. The new bridge will be the highest of the cable-stayed type in Latin America and forms part of the road connecting Malaga with Los Curos. The bridge measures 148.3m high by 653m long and work on its deck has been completed. The bridge has cost US$35.3 million to build, with the work being carried out by contractor Sacyr. The new bridge is located close to San Andres and the project has included a number of challenges
  • Delay for tenders on key Colombian highways
    April 28, 2014
    The tender process has been extended for three highway concession packages in Colombia, according to Business News Americas. The country's national infrastructure agency (ANI) has extended the bid deadlines for the Pacífico 2 (Bolombolo-La Pintada), Pacífico 3 (La Pintada-La Virginia) and Río Magdalena 2 (Remedios-Puerto Berrío) projects. The three highway concessions are worth a total of US$1.2 billion and form part of Colombia’s Autopistas para la Prosperidad highway programme. ANI opted to delay the tend
  • German VDMA organisation members optimistic
    February 7, 2020
    The German VDMA construction equipment manufacturers organisation members are optimistic for the future.