Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Work commencing on key New Zealand tunnel link
    August 3, 2012
    New Zealand prime minister John Key led an official ground-breaking ceremony this week to allow the start of excavation work for two new 2.4km-long motorway tunnels beneath suburban Auckland. The Waterview Connection project is on schedule to begin its main construction phase next year, and the prime minister was on hand to turn the first soil for a 30m-deep trench which is needed to allow access for the tunnels’ southern approach trench in the west Auckland suburb of Owairaka.
  • Tolling model for funding road development
    April 4, 2017
    Road tolling is being used worldwide as a way to develop highway infrastructure, with road users paying for access. Tolled roads are not a new concept and date back centuries, but in recent times, as governments have struggled to fund highway development programmes directly, tolling has increased in popularity worldwide. In Africa, Asia, Europe, Latin America and North America, tolled highways are now extremely well established. The specifics of the business models vary but state-owned toll-road firms ty
  • Norwegian tunnel project being delayed
    April 2, 2020
    A Norwegian tunnel project is now being delayed.
  • Just stop arguing and build the thing
    December 15, 2017
    The news that the preferred route has been announced for a new road and tunnel link that will bypass the UK’s famous Stonehenge stone circle comes after years of debate. The project is for the construction of a new 13km dual carriageway link and includes a 2.6km stretch of tunnel, which is the subject of some controversy. Because of the archeological importance of the area, the tunnel has been decided as being the best option for the new route. Building a tunnel will allow much of the important archeologi