Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Colombia’s troubled tunnel project completion due
    April 26, 2017
    The completion of work on Colombia’s troubled tunnel project is now finally in sight. A new contractor will be selected by Colombia's National Road Institute (Invias) to complete the last section of work required on the La Linea Tunnel. The winner of the tender process will be announced on 13th June 2017. An additional US$50 million is being budgeted by the Colombian authorities to complete the work. It is expected that in all, finishing the project will cost $86.6 million. Work still to be carried out incl
  • New tunnel link proposed for Colombia
    July 23, 2013
    Even as work continues on La Linea tunnel in Colombia, the country’s government has received a proposal for an additional tunnel link. A consortium made up of Colombian companies and Italian firms has suggested building a new tunnel to link Quindio and Tolima. Odinsa, Mincivil, Impregilo and Salini are involved in the consortium and have suggested a PPP as being a possible model under which to construct the link, which could cost in the order of US$531 million and would be 8.5km long. The economic case for
  • Colombia tunnel delays continue
    September 26, 2016
    Further delays have hit the project to build the La Linea Road Tunnel in Colombia. As a result the tunnel will not be open to traffic until the first half of 2018. This is the latest in a series of delays that have held back the opening of the tunnel. Previous delays have been caused by the discovery of geological conditions that were far more challenging than originally expected as well as problems over insurance cover for the construction firms. When open to traffic the new link will stretch 8.6km and wil
  • Colombia tunnel construction cost climbs
    January 25, 2018
    Work on the La Linea Tunnel project in Colombia has cost considerably more than first anticipated. The National Road Institute (Invias) says that the bill so far tops US$774 million. Extra costs of around $281.5 million have been incurred due to the need to drive a pilot tunnel as well as for three additional tunnel stretches as well as bridges along the approaches to the main tunnel. The project is now expected to be complete by the end of 2018, somewhat later than originally expected.