Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • IRF awards Parsons for its East End Crossing work in the US
    August 7, 2015
    The International Road Federation (IRF) has awarded its Global Road Achievement Award for project finance and economics to Parsons for the East End Crossing of the Ohio River Bridges Project. Parsons, which served as the technical advisor for the implementation of a public-private partnership (PPP), received the award for achievements in cost savings and accelerated project delivery. This was done through the PPP procurement process for the development, design, construction, financing, operation and m
  • Advances in tunneling technology offer efficiency
    October 18, 2017
    New developments in tunnelling technologies offer contractors greater efficiencies when constructing new bores. Tunnel boring machines (TBMs) are widely being used in major projects such as the Brenner Base Tunnel in the Austrian Alps. Full face TBMs are highly sophisticated machines featuring a rotating drilling head, which removes the material, and, depending on the type of construction, secures the excavated tunnel with shotcrete, rock bolts and wire mesh or prefabricated segments of reinforced concrete.
  • New section planned for the Pennsylvania Turnpike
    March 27, 2020
    A new stretch of road is needed for the Pennsylvania Turnpike.
  • Key deals show strength of Tolling solutions sector
    September 26, 2013
    The world’s leading tolling solution providers have achieved significant deals in recent months emphasising the importance of their latest and proven technology. Guy Woodford reports Kapsch TrafficCom North America (Kapsch), part of Kapsch TrafficCom Group, has been awarded a five-year US$30 million contract by Canadian Tolling Company International (Cantoll). The contract will see the leading tolling technology manufacturer supply its next generation TDMA V6 Interior Transponder, also known as an onboar