Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Mexico continues plans for major transport network programme
    September 23, 2014
    Mexico is continuing with its plans for a series of major transportation projects aimed at boosting connectivity. The country’s Secretariat of Communications and Transportation (SCT) says that work is underway on 110 of the country’s 128 planned bridge projects. Construction of the remaining 18 bridges is commencing in due course. And 23 of the 110 bridges being built at present are being opened to traffic shortly, with a further 46 opening in November 2014 and 38 opening in December 2014. The project to wi
  • Bogota transport infrastructure boost
    April 26, 2016
    The Colombian Government is investing in road infrastructure development, with a large portion of the budget being directed to Bogota. The road infrastructure programme includes 22 projects that will help cut chronic congestion in Colombian capital Bogota. Construction works for Avenida Longitudinal de Occidente (ALO) road expansion are expected to start in the first half of 2016. These will run from the Mondonedo intersection to Boyaca Avenue, in the southern part of the city. The budget for this project i
  • Colorado express lanes opening
    November 29, 2021
    Express lanes are opening on I-25 in Colorado.
  • New bridge planned for key Indonesia link
    July 22, 2013
    A feasibility study worth US$199 million will be carried out for the planned Sunda Straits Bridge in Indonesia. The bridge itself is expected to cost close to $20 billion to construct. It will be of major economic importance for Indonesia by providing a direct road link between the islands of Sumatra and Java. The link will connect Sumatra directly to Indonesia’s capital, Jakarta, and the bridge is expected to be 27km long in all. The Sunda Straits Bridge will actually be a series of links connecting the sm