Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Analysing green Australian procurement practices
    December 16, 2014
    Adriana Sanchez and Keith Hampson of the Sustainable Built Environment National Research Centre (SBEnrc) discuss green procurement Procurement has a key role impacting the lifecycle of a construction project and can serve to drive many sustainability outcomes. Green procurement in particular can be used as a strategic tool to promote certain behaviour and as an environmental policy instrument to translate environmental policies into environmentally sustainable project processes, products and services. Th
  • ARTBA predicts growth in transport construction
    December 2, 2016
    Modest growth in transport construction is predicted in the US in 2017 by the American Road & Transportation Builders Association (ARTBA). According to a report by ARTBA chief economist, Dr Alison Premo Black, total transportation construction and related market activity is expected to grow 1.3% in 2017, driven largely by increases in highway and bridge private construction activity supporting residential and commercial developments. In 2017, the market is expected to reach US$247.8 billion, up from $244
  • Underground expansion pushes tunnelling market
    June 13, 2012
    Infrastructure investment means that the road tunnel construction sector is healthy due to demand for new links – Mike Woof reports With many emergent nations investing heavily in infrastructure, the tunnelling sector is seeing extensive business at present. Tunnels provide key links in mountainous areas or in congested cities where building roads on the surface may not be practical. In Asia and Latin America, many key road connections are now being built underground to pass challenging terrain or provide
  • Bridge or tunnel choice
    April 25, 2012
    Plans for a €325million (US$423.76million) fixed transport link project in Estonia will be presented to the country’s Government in early 2012, according to a senior road planning official.