Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Improving safety for cyclists
    November 15, 2013
    New systems in development for protecting vulnerable road users - Mike Woof writes In many European countries the number of people using bicycles for commuting are increasing. This is being actively encouraged by city authorities as it offers an effective way to reduce traffic congestion, lower exhaust emissions and also improve public health. The Netherlands and Denmark have long had high percentages of commuters opting to use bicycles and other European countries are looking to capitalise on the experienc
  • Importance of continued transportation investment
    February 27, 2012
    The US infrastructure network requires urgent attention - * T Peter Ruane. America's transportation infrastructure was once the "shining light on top of the hill." Major investments in a national highway, bridge, transit, airport, port and waterway system during the 20th century paid great dividends. The free and efficient flow of goods and people across the 50 states led to unparalleled economic expansion. The mobility and prosperity resulting from an interconnected infrastructure was a model for the world
  • Importance of continued transportation investment
    May 2, 2012
    The US infrastructure network requires urgent attention - * T Peter Ruane. America's transportation infrastructure was once the "shining light on top of the hill." Major investments in a national highway, bridge, transit, airport, port and waterway system during the 20th century paid great dividends. The free and efficient flow of goods and people across the 50 states led to unparalleled economic expansion. The mobility and prosperity resulting from an interconnected infrastructure was a model for the world
  • Risk management hinders Estonian projects
    May 9, 2022
    A National Audit Office report noted poor documentation of the work that had been completed and why it was later changed.