Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Tunnel Boom in Central and Eastern Europe
    September 15, 2015
    Following the success of the 41st World Tunnel Congress held in Croatia last May, World Highways looks at two signi_ cant projects in Slovakia and Serbia – Adriana Potts reports Central and Eastern Europe is buzzing with a number of major projects being developed - including highways, bridges and tunnels – and with many more in the pipeline. The region is expected to be highly active with plans for developing infrastructure in the next two decades, according to Davorin Koli , president of the Croatian
  • Taiwan road contract faces delays
    October 9, 2015
    The 38.8km improvement project for Taiwan’s Suhua Highway now looks to be delayed until 2019. The opening of the route is being delayed by a combination of factors including landslides and archeological discoveries. The improvement works include upgrades to a number of key bridges and mountain tunnels like sections from Suao to Dongao, Nanao to Heping and Heping to Daqingshui. The project is costing US$1.42 billion. The project was originally scheduled to be completed in 2017. The delays involve relocation
  • Speed and precision make for perfect tunnelling combination
    May 21, 2014
    Speed and precision have been the hallmarks of a number of major road tunnelling projects across the globe over the last 12 months, as the latest sector equipment from leading manufacturers has found itself in high demand. Guy Woodford reports Herrenknecht tunnel boring machines (TBM) have been busy tunnelling under major Chinese rivers, demonstrating phenomenal speed, top safety levels and extreme precision while playing a key role in the construction of road tunnels in the Yangtze River Delta. The Yang
  • Chile-Argentina tunnel loan for bidding
    December 14, 2016
    Further progress is being made with the Agua Negra Tunnel project, which will connect Chile with Argentina. A loan worth US$40 million is being provided by the Inter-American Development Bank (IADB). This loan will help deliver the bidding process for the project. Several bidders are being pre-qualified for the tender process. Construction of the tunnel itself is expected to take eight ant a half years with the work estimated to cost $1.6 billion. The tunnel will provide a safer and more reliable route than