Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Morocco extraction site service capability
    July 15, 2016
    Phosphate extraction is carried out on a huge scale in Morocco in harsh, hot and often remote locations. Servicing this equipment is no easy task given the conditions, with special machines having to be used Phosphate is in high demand. It is used in fertilizer, detergent and food additives. However its fastest growing market is in the manufacturing of lithium-ion batteries, now being used widely for commercial goods as well as electric vehicles. As Morocco is the world's third-largest producer of phosphate
  • Florida’s Gateway project is underway
    September 29, 2023
    Florida’s Gateway Expressway project is underway.
  • Develop the Silk Roads, boost economic growth
    February 28, 2012
    Tony Pearce, honorary life member and former director-general of IRF Geneva, recalls the history of the Silk Roads, highlights their continued economic relevance and introduces IRF's active long-term commitment to their rehabilitation. The Silk Roads had their origins in a Chinese military mission in 138BC to purchase horses in Central Asia's Fergana Valley that were reputed to run so fast that they sweated blood. When General Chang Ch'ien reached Fergana, now in Uzbekistan, he found that the fabled horses
  • Tunnel waterproofing solutions
    February 29, 2012
    Tunnels are the highest value assets on a highway, making their operation, safety and maintenance of paramount importance. Patrick Smith reports