Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • How Florida paved the way for availability payments in the US
    November 21, 2014
    New financing models have been used to deliver key transport links in the US - * Patrick D Harder and Brandon J Davis Florida Department of Transportation’s (FDOT) public-private partnership (PPP) programme has made impressive progress, setting precedents for US transportation planning and funding. On March 26th 2014, FDOT opened 16km of new reversible express lanes as part of its US$1.8 billion I-595 Corridor Roadway Improvements Project. Just a few months later, on August 3rd 2014, FDOT opened twin tunnel
  • New bridge in Colombia using materials from CEMEX
    March 7, 2018
    A new bridge project in Colombia is benefiting from the supply of concrete from CEMEX Latam Holdings The project is to build a new bridge for Colombia’s Río Magdalena 2 Highway, with the road being one of the primary infrastructure projects currently under development in the country. CEMEX Colombia is supplying concrete for several essential elements of the project, including a viaduct over the Magdalena River that will become one of the longest bridges in the country.
  • Europe’s road safety targets at risk
    July 10, 2015
    This new analysis has been published by the European Transport Safety Council (ETSC). According to the ETSC data, 2014 showed the lowest annual reduction in EU road deaths since 2001. In all 25,845 people were killed in road crashes in the 28 nations of the EU during 2014. This represented a decrease of just 0.6% compared to 2013. EU member states now need to cut deaths by almost 8% each year until 2020 to meet the target set in 2010 to halve deaths within a decade.
  • Colombia road tolling contract
    June 20, 2016
    DEVISAB recently awarded a major contract to modernise the control centre and renew three toll plazas on a highway linking the municipality of Chia with Girardot and Soacha, west of capital Bogota Indra already has a strong position in the Colombian infrastructure and transport industry. The firm operates flagship projects such as the Bogota-Villavicencio divided highway and the Medellin urban mobility system The contract is to renovate the technology used at three toll plazas and a control centre fo