First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.
February 12, 2016 Read time: 2 mins

The 6126 Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.


"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

View Trinity in action by clicking here.
%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.merseygateway.co.uk/live-view Visit www.merseygateway.co.uk/live-view false http://www.merseygateway.co.uk/live-view false false%>

For more information on companies in this article

Related Content

  • Mersey Gateway Project reaches half-way point across the Mersey
    March 10, 2017
    The Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey. Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon. When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes. “We’re now more than 50
  • High court drama expected at Highways UK event, NEC, Birmingham
    November 7, 2016
    What happens when a highways services employee is prosecuted for failing to follow established safety procedures? How would a courtroom drama unfold for the accused and the employer?
  • Zoomlion’s new RT series of mobile cranes offer up to 61m of reach
    January 6, 2017
    Large cabs and extensive reach capabilities are key features of Zoomlion’s new RT series of mobile cranes built specifically for the North American market. According to Larry Tate, service and parts manager for Zoomlion, “we’ve used the best components available (and) improved parts availability too.” The RT65 mobile crane features a longer, five-section, 43m boom. “That’s without the jib,” Tate said. “Pull out the jib and the insert and you get another 18m.” This extra reach has extensive benefit to contra
  • Zoomlion’s new RT series of mobile cranes offer up to 61m of reach
    March 11, 2014
    Large cabs and extensive reach capabilities are key features of Zoomlion’s new RT series of mobile cranes built specifically for the North American market. According to Larry Tate, service and parts manager for Zoomlion, “we’ve used the best components available (and) improved parts availability too.” The RT65 mobile crane features a longer, five-section, 43m boom. “That’s without the jib,” Tate said. “Pull out the jib and the insert and you get another 18m.” This extra reach has extensive benefit to contra