First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.
February 12, 2016 Read time: 2 mins

The 6126 Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.


"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

View Trinity in action by clicking here.
%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.merseygateway.co.uk/live-view Visit www.merseygateway.co.uk/live-view false http://www.merseygateway.co.uk/live-view false false%>

For more information on companies in this article

Related Content

  • Ausa’s telehandler proves popular at Conexpo
    March 11, 2014
    Ausa’s newest and smallest telehandler, the T 144 H plus, was receiving a lot of attention on the manufacturer’s stand at Conexpo. “We’ve had a lot of interest, especially in this machine,” said Mark Benfield, Ausa’s area manager for USA and Canada. “Some people like it more than skid steers because you get more reach and more lift for the same size of the machine.
  • XCMG to create R&D base in the United States
    January 6, 2017
    Leading Chinese construction equipment manufacturing firm XCMG has revealed plans to open a new research and development facility in the United States. Speaking at bauma 2013 Wang Yansong, the company’s vice president, said, “In the second half of this year we are planning to build a R&D centre in the United States. It’ll take about half a year to finish construction. It should open in 2014.” While Yansong would not reveal how much XCMG was investing in the US site, he said it was due to America, along with
  • XCMG to create R&D base in the United States
    April 16, 2013
    Leading Chinese construction equipment manufacturing firm XCMG has revealed plans to open a new research and development facility in the United States. Speaking at bauma 2013 Wang Yansong, the company’s vice president, said, “In the second half of this year we are planning to build a R&D centre in the United States. It’ll take about half a year to finish construction. It should open in 2014.” While Yansong would not reveal how much XCMG was investing in the US site, he said it was due to America, along with
  • A future UK government should focus more on potholes and road safety
    April 10, 2015
    With a national UK election looming next month, a future government must make road safety a top priority, said the Institute of Advanced Motorists (IAM). Half of motorists in a recent survey of 2,156 people, and conducted IAM in March, said the current administration has not given the issue as much attention as is needed. The number one issue that the government should be focussing on, according to 70% of respondents, is the reduction of the number of potholes. The backlog of repairs now tops more