First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.
February 12, 2016 Read time: 2 mins

The 6126 Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.


"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

View Trinity in action by clicking here.
%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.merseygateway.co.uk/live-view Visit www.merseygateway.co.uk/live-view false http://www.merseygateway.co.uk/live-view false false%>

For more information on companies in this article

Related Content

  • Erlau’s Sideflex tyre protection system deflects rock debris away from tyres
    April 18, 2013
    Identifying the cost and downtime caused by damaged sidewalls on dumptrucks used in mining and quarry applications, Erlau has developed the Sideflex tyre protection system, which is claimed to be capable of deflecting rock debris away from tyre walls. Using bolt-on segments that form an Armadillo-like layer of protection covering the outer sidewall of an earthmoving tyre, Sideflex affords high-speed use, unlike traditional tyre chain protection systems, which offer limited speeds in use. “Comprehensive tyre
  • Perkins will demonstrate how its engine will meet EU Stage IV/US Tier 4 Final emissions regulations
    January 6, 2017
    Perkins will showcase a complete line-up of Stage IV/Tier 4 Final engine solutions at Bauma, ahead of the new legislation next year. The four cylinder 854F-E34TA will demonstrate much of the technology on offer, as it uses Selective Catalytic Reduction (SCR) with an exhaust additive, plus a Diesel Oxidation Catalyst (DOC). Both Perkins’ 3.4 and 4.4-litre engine lines make do without a Diesel Particulate Filter (DPF), though the larger 7 litre will use a DPF as well.
  • Perkins will demonstrate how its engine will meet EU Stage IV/US Tier 4 Final emissions regulations
    February 7, 2013
    Perkins will showcase a complete line-up of Stage IV/Tier 4 Final engine solutions at Bauma, ahead of the new legislation next year. The four cylinder 854F-E34TA will demonstrate much of the technology on offer, as it uses Selective Catalytic Reduction (SCR) with an exhaust additive, plus a Diesel Oxidation Catalyst (DOC). Both Perkins’ 3.4 and 4.4-litre engine lines make do without a Diesel Particulate Filter (DPF), though the larger 7 litre will use a DPF as well.
  • Euro Road Safety launches Insight vehicle sign for learner drivers
    October 17, 2018
    Euro Road Safety, designers of road safety products, has launched Insight to provide learner and newly qualified drivers with extra confidence that they are visible. The Insight system is made from polypropylene and protrudes no more than the vehicle manufacturer’s factory-fitted wing mirror, explained Phil Thorpe, the inventor of the system. With new regulations now allowing learner drivers on UK motorways it has become even more important for learners to stay visible on the road. The design of th