First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.
February 12, 2016 Read time: 2 mins

The 6126 Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.


"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

View Trinity in action by clicking here.
%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.merseygateway.co.uk/live-view Visit www.merseygateway.co.uk/live-view false http://www.merseygateway.co.uk/live-view false false%>

For more information on companies in this article

Related Content

  • Wacker Neuson adds to telehandler range
    April 19, 2013
    Wacker Neuson has added two compact telescopic handlers to its range – the TH412 and the TH625. The machines offer maximum heights of 4.31m and 5.73m respectively, with lift capacities of 1.2tonnes and 2.5tonnes. Despite their compact dimensions they retain large telescopic-handler design features, such as all-wheel steering and generously-sized cabs, standard on the TH625 and optional on the smaller model. The two loaders are equipped with Wacker’s VLS vertical lift system, which avoids overloading throug
  • NDT sensor fusion in structural pavement condition surveys
    February 27, 2017
    Early detection of pavement defects and the causes of deterioration is essential for effective maintenance planning, writes Dr Alena Uus* There is a need for optimisation and development of UK highway survey methods that would provide comprehensive information on the surface and subsurface pavement condition and operate at traffic speed, which eliminates the requirement for lane closures. Performance of non-destructive testing (NDT) methods commonly employed in pavement condition surveys can be potent
  • Copy of LeeBoy expansion strategy targets emerging markets
    October 16, 2014
    During the recent Conexpo event in Las Vegas, Kelly Majeskie, President of The LeeBoy Group, spoke about his expansion plans for the business “We’ve been working on a couple strategies for LeeBoy” said Majeskie, “an overseas growth strategy and a more focused approach to the US market. Like most businesses we saw a major downturn when the US housing market took the big hit in 2008/9.
  • Ritchie Bros’ first regional auction shown live at INTERMAT
    April 19, 2012
    Ritchie Bros Auctioneers’ first multi-million pound auction at its new regional site in Donington Park, UK, was shown live at INTERMAT. The company registered more than 630 online and on-site bidders from 50 countries to bid on more than 675 heavy plant equipment items and trucks. Two unused Volvo L90F wheeled loaders sold to an online bidder from Australia for €147,000 each.