First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.
February 12, 2016 Read time: 2 mins

The 6126 Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.


"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

View Trinity in action by clicking here.
%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.merseygateway.co.uk/live-view Visit www.merseygateway.co.uk/live-view false http://www.merseygateway.co.uk/live-view false false%>

For more information on companies in this article

Related Content

  • Cat launches 336E H hybrid excavator at bauma
    January 6, 2017
    Described as a “game-changer” by Gary Stampanato, vice president of Caterpillar’s excavation division, the Cat 336E H hybrid excavator will be officially launched at the bauma show. Using new hydraulic technology developed by Cat, the hybrid machine is said to deliver uncompromised performance, durability and reliability. Cat claims the 336E H delivers industry-leading productivity, with up to 50% greater fuel efficiency over the 336D. It is also said to use up 25% less fuel than a standard 336E, and up to
  • Cat launches 336E H hybrid excavator at bauma
    April 9, 2013
    Described as a “game-changer” by Gary Stampanato, vice president of Caterpillar’s excavation division, the Cat 336E H hybrid excavator will be officially launched at the bauma show. Using new hydraulic technology developed by Cat, the hybrid machine is said to deliver uncompromised performance, durability and reliability. Cat claims the 336E H delivers industry-leading productivity, with up to 50% greater fuel efficiency over the 336D. It is also said to use up 25% less fuel than a standard 336E, and up to
  • Liebherr’s PR 736 dozer launched on US market at Conexpo 2014
    January 6, 2017
    The PR 736 dozer being introduced to the US market at Conexpo 2014 is the first model in Liebherr’s new Generation 6 series and is said to offer customers increased efficiency and lower fuel consumption and CO2 emissions. Among the innovations on the Generation 6 machine models, including the 20-25tonne service weight PR 736, are electronic travel speed regulation with an integral eco-function, and pro-active power control.
  • Liebherr’s PR 736 dozer launched on US market at Conexpo 2014
    January 24, 2014
    The PR 736 dozer being introduced to the US market at Conexpo 2014 is the first model in Liebherr’s new Generation 6 series and is said to offer customers increased efficiency and lower fuel consumption and CO2 emissions. Among the innovations on the Generation 6 machine models, including the 20-25tonne service weight PR 736, are electronic travel speed regulation with an integral eco-function, and pro-active power control.