First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.
February 12, 2016 Read time: 2 mins

The 6126 Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.


"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

View Trinity in action by clicking here.
%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.merseygateway.co.uk/live-view Visit www.merseygateway.co.uk/live-view false http://www.merseygateway.co.uk/live-view false false%>

For more information on companies in this article

Related Content

  • Sobratema predicts $6 billion-a-year spend on construction equipment
    April 18, 2013
    More than US$ 800 billion of major infrastructure investment projects will drive increasingly high levels of demand for the global construction equipment supply sector in Brazil over the next five years, according to a new report from Sobratema, the Brazilian association of technology for construction and mining. The entire chain of supplies and services will benefit from a massive Brazilian road-building and social housing construction boom as the country gears up to host the 2014 soccer world cup and the
  • INTERMAT launch for tracked pump
    January 6, 2017
    The BSC 1409 D from Putzmeister is a self-propelled concrete pump designed specifically for concreting drilled piles on unfinished surfaces. In contrast to using truck-mounted concrete pumps for concreting drilled piles, it does not need supports to be set up each time it changes location. Compared to concreting with a delivery pipe, placement speed with the tracked concrete pump is now said to be considerably higher.
  • INTERMAT launch for tracked pump
    April 12, 2012
    The BSC 1409 D from Putzmeister is a self-propelled concrete pump designed specifically for concreting drilled piles on unfinished surfaces. In contrast to using truck-mounted concrete pumps for concreting drilled piles, it does not need supports to be set up each time it changes location. Compared to concreting with a delivery pipe, placement speed with the tracked concrete pump is now said to be considerably higher.
  • Sennebogen shows dragline at INTERMAT
    January 6, 2017
    While draglines are now a rarity, Sennebogen showed its 50tonne operating weight duty cycle crawler crane, the 650HD, with 2.33 dragline bucket. The machine is one of a 10-model range with operating weights from 20-180tonnes and engines between 119 and 708kW. It can be used in civil engineering, mining, demolition or material handling.