First bridge deck section joined on UK’s Mersey Gateway project

The Mersey Gateway bridge project near Liverpool in England passed a milestone recently with the first joining of two of the deck sections.
June 30, 2017 Read time: 3 mins
Mersey Gateway project: joined-up bridge building

The Mersey Gateway bridge project near Liverpool in England passed a milestone recently with the first joining of two of the deck sections.


The key segments, as the sections are called, link the north approach viaduct to the north pylon deck span and are the first of four deck-joins scheduled for this summer. In total, there are five sections of bridge deck and approach roads that need to be joined.

Under construction is a six-lane cable-stayed structure with three towers that will span the Mersey River’s expansive mud flats between the towns of Runcorn and Widnes near Liverpool.

Including the approach viaducts on each side, the project will be 2.3km long with a river span of 1km. The main bridge deck will be reinforced concrete. The 80m-high central tower will be shorter than the two outer towers, where the north tower will be 110m high and the south tower will reach 125m.
 
The deck is being built outwards from each of the three pylons at a rate of around 6m a week.
 
As well as being linked to each other, the north and south main bridge deck sections also need to be linked to the approach roads – the viaducts built over the saltmarsh and the canals – approaching the river.

“We have now linked the sections of deck together by bridging the gap between the two decks with four steel restraint struts that resemble giant bolts and a concrete pour,” said Hugh O’Connor, general manager of Merseylink, the consortium building the bridge.
 
“Once the concrete has set, the decks are further locked together with external post-tensioned tendons. This is a major step for the project and we remain on target to complete the final three joins this summer with the bridge expected to open to traffic this autumn.”
 
It took around two hours to pour 40m³ of concrete to fill the 2m gap between the north approach viaduct and north pylon deck span.
 
“We could complete the pour only once the form traveller was moved into position and the mould had set. The gap between sections was only two metres wide, but runs the entire 32 metres width of the bridge deck,” said O’Connor. “Around 18 hours after the pour, the concrete sets to full load-bearing strength.”

Merseylink Consortium was appointed by Halton Borough Council to a 30-year design, build, finance and operate contract. Equity partners are 2378 Macquarie Capital Group, BBGI, and 1340 FCC Construcción. The construction joint venture is made up of Kier Infrastructure and Overseas, 1026 Samsung C&T and FCC Construcción.  Emovis will deliver and operate tolling through its merseyflow brand. 

For more information on companies in this article

Related Content

  • First concrete beam raised for new Mersey bridge link
    December 11, 2015
    The first concrete bridge beam for a junction on the new Mersey Gateway route has been lifted into place. Work is underway on a major road junction for the Mersey Gateway Project, with the first of 156 of the concrete beams has been lifted into place as work ramps up at a major road junction. A 550tonne capacity crane lowered the 106tonne beam into position at the Bridgewater junction in Runcorn, where the new Astmoor Bridgewater viaduct is being built over the Bridgewater canal. Two elevated slip roads ar
  • Mersey Gateway: Consortia Talks
    April 4, 2012
    The competitive dialogue phase of the Mersey Gateway Project has begun. The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months. The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013. The value of the construction phase of the project, including land, is estimated at US$961milli
  • Mersey Gateway shortlist revealed
    March 14, 2012
    The shortlist of three bidders for the US$942million (£600m) plus Mersey Gateway Project in North West England has been revealed.
  • Mersey Gateway Bridge project progress
    October 6, 2016
    Work is well in hand on the Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high. A specialist automatic climbing system is being used to construct the