Final beam for Gerald Desmond Bridge replacement

The US$1.47 billion project was started in 2013 and open later this year.
By David Arminas May 1, 2020 Read time: 2 mins
Final beam for California’s first cable-stayed bridge for vehicles (photo courtesy Gerald Desmond Bridge Replacement Project)

The final steel beam has been installed for the replacement Port of Long Beach bridge - California’s first cable-stayed bridge for vehicles.

The beam was carefully lifted into position almost two years after construction began and which is expected to open later this year. The US$1.47 billion project to replace the current Gerald Desmond Bridge was started in 2013. The current bridge, finished in 1968, is a through arch steel structure that carries four lanes of Ocean Boulevard from Interstate 710 in Long Beach,

The new bridge will provide a higher clearance for cargo ships, possess a high degree of structural resilience against earthquakes and have a 100-year minimum lifespan. There will be six traffic lanes and four emergency shoulders, a bike and pedestrian path with scenic overlooks and more efficient transition ramps and connectors to improve traffic flow.

Assembling the main span over the Port’s Back Channel began in April 2018 with the lifting of the initial bolted sections of steel flooring to be attached to the first set of cables from the two 515-foot-tall towers.

Main-span construction requires deck sections to be added equally on both sides of the towers. Each floor beam is about 140 feet long and 10 feet tall, weighs about 32 tons and is connected to other steel components known as edge girders with more than 200 bolts.

Once a section of floor beams is bolted together, crews attach it to the tower with dozens of cables, then place pre-cast concrete road deck panels that form the road deck. There are 117 floor beams that support a main span that rises 205 feet over the water.

Additional major tasks left to do include a post-tensioning process by which cables are installed horizontally through the floor and pulled tight to increase the strength of the main span concrete deck.

The project is a joint effort by Caltrans – the California Department of Transportation - and the Port of Long Beach, with additional funding from the US Department of Transportation and the Los Angeles County Metropolitan Transportation Authority.

Related Content

  • New NY Bridge - Tappan Zee - main span towers poured
    December 16, 2016
    One of the largest US infrastructure projects is nearer completion after recent topping out of the eight main span towers of the New NY Bridge. The final concrete pour was in mid-December and all piles - more than 1,000 - have been installed in Hudson River. To date, 3,000 roadway panels for the approaches - making 5.5km in length - have been installed, according to the New York State Thruway Authority, owner of the New NY Bridge project. The New NY Bridge, also called the Tappan Zee Bridge, is on tra
  • LA’s Ribbon of Light viaduct cast into darkness
    January 10, 2024
    Thieves have been pulling copper wiring out of electrical boxes Los Angeles’ 6th Street Viaduct and selling it for scrap, prompting police to report that “the Grinch stole all the Christmas lights”.
  • Europe closes in on the crossings
    September 27, 2017
    The Mersey Gateway bridge project off England’s west coast passed a milestone recently with the first joining of two of the deck sections. The key segments, as the sections are called, link the north approach viaduct to the north pylon deck span and are the first of four deck-joins scheduled for this summer. In total, there are five sections of bridge deck and approach roads that need to be joined.
  • LA bus lanes planned
    May 17, 2022
    New bus lanes are planned for Los Angeles.