EU funds set for renovation of the Karawanks Tunnel

The European Commission will provide €25 million for renovation of the 7.8k-long Karawanks Tunnel, a motorway link between Austria and Slovenia. The Karawanks is a 120km-long mountain range between Slovenia to the south and Austria to the north. Around €6.5 million will go towards planning and €18 million will be set aside for reconstruction.
July 18, 2017 Read time: 1 min

The 2465 European Commission will provide €25 million for renovation of the 7.8k-long Karawanks Tunnel, a motorway link between Austria and Slovenia.

The Karawanks is a 120km-long mountain range between Slovenia to the south and Austria to the north.

Around €6.5 million will go towards planning and €18 million will be set aside for reconstruction.

Work will include a rescue route as well as updated fire protection facilities and communication system.

The renovation has a total budget of around €115 million, of which Austria will pay €65.3 million. Construction work will begin in 2018.

Construction of the motorway tunnel began in 1986 and it opened in 1991. It connects the Austrian Karawanken Autobahn A11 from Villach with the A2 motorway, leading across the border to the Slovenian cities of Kranj and Ljubljana.

The road tunnel – of which there is a parallel rail tunnel that opened in 1906 - is part of the transport 8111 axis Munich-Salzburg-Ljubljana-Thessaloniki, also called Pan-European Corridor-X.

For more information on companies in this article

Related Content

  • Austria-Slovenia tunnel project awarded
    August 9, 2018
    Construction of the second tube of the Karawanks Tunnel connecting Austria and Slovenia is now going ahead. The work will be headed by Austrian contractors, ARGE Swietelsky Tunnelbau and Swietelsky Baugesellschaft. The 7.8km-long tunnel route runs under the Alpine Karawanks mountain range. The Austrian motorway operator Asfinag is investing around €168 million into the project, while the European Commission is providing €25 million. The work being carried out will include building new rescue routes as wel
  • Breakthrough for Slovenian Karavanke Tunnel
    April 2, 2024
    The existing tunnel Karavanke Tunnel tube between Austria and Slovenia opened in 1991.
  • Legal challenge to Austria-Slovenia tunnel contract award
    August 23, 2018
    A legal challenge has now been launched against the tender award for the second tube for the Karawanks/Karavanke Tunnel project between Austria and Slovenia. The challenge has been launched by the two bidders that were unsuccessful for the project, Kolektor CPG and Euro-Asfalt. The 7.8km-long tunnel route runs under the Alpine Karawanks/Karavanke mountain range, connecting the Austrian Autobahn A11 from Villach with the A2 highway, running across the border to the Slovenian cities of Kranj and Ljubljana.
  • Slovenia tunnel contract reselection
    December 6, 2018
    The contract for the second drive for the Karavanke tunnel connecting Slovenia with Austria is now once more being tendered. The project was awarded earlier this year to the Turkish contractor, Cengiz Insaat Sanayi Ve Ticaret. However this deal was then annulled and the firm prevented from reapplying. The Turkish company had submitted a bid of €89.3 million for the work. However this had to be rejected as the actual estimate to build the link sets a pricetag of some €121.5 million. The Slovenian road opera