Demolition starts on Seattle’s Alaska Way Viaduct

Demolition of the Alaska Way Viaduct in the northwest US city of Seattle is underway, including the filling in of a redundant road tunnel.
June 14, 2019 Read time: 2 mins
Coming down: Demolition of Seattle’s Alaska Way Viaduct, a 1950’s structure, began this winter (pic courtesy Philip Renaud)

Demolition of the Alaska Way Viaduct in the northwest US city of Seattle in Washington State is underway, including the filling in of a redundant road tunnel.

Demolition contractor Kiewit Infrastructure West picked up the contract estimated at around US$94 million, according to media reports. Work is expected to take up to two years and includes filling in the Alaska Way’s Battery Street Tunnel.

For each segment of the viaduct, the contractor is removing the road decks, then girders and crossbeams and finally the support columns. During demolition, barriers are installed to protect nearby buildings and water is sprayed on the work to keep down dust.

Tunnel work includes decommissioning and removing the utility and mechanical systems, removal of hazardous material from the tunnel and, when finished, the sealing of the two entrances.

Kiewit decided against using conveyor belts to move the material into the Battery Street Tunnel. Instead, rubble is trucked to a nearby sorting area where rebar is removed. The material is crushed into small piece and loaded onto side-dumping trucks that carry the debris to openings along the tunnel route that lead directly down into the tunnel itself. The trucks dump the material into a steel funnel over the openings and down it goes into the tunnel. It takes less than a minute for the material to crash down into the tunnel where it is then levelled out by workers. Vibratory rollers spread and compact the material in layers.

Prior to the demolition work, there were public petitions to keep the Battery Street Tunnel open for pedestrian and bicycle use. However, the Washington State Department of Transportation decided that the structure, in need of repair,  would have been extremely expensive to upgrade to modern seismic standards – an important feature for any structure along the west coast of the US and up into Canada. The region lies along the infamous San Andreas Fault making it prone to earthquakes.

The new Alaska Way’s tunnel lies directly under the old viaduct and was the subject of a World Highways Key Project Report in 2017.

<%$Linker:

2

External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external https://www.worldhighways.com/categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false https://www.worldhighways.com/categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>

 

Related Content

  • Bertha ends her Alaskan Way voyage in Seattle
    December 21, 2017
    Seattle's State Route 99 viaduct is coming down. David Arminas was on site. Bertha, the world’s largest diameter earth pressure balance tunnel boring machine, with a cutterhead diameter of 17.5m, is no more. Her 2.7km journey underneath the waterfront area of Seattle finished on April 4 and the power went off for the last time on an extraordinary TBM that had finally completed an extraordinary job. “A small sidewalk job would have had more impact on city traffic than we have had,” says Brian Russell a v
  • Major Norwegian tunnel project opening
    September 20, 2019
    Norway’s landmark tunnel project is due to open at the end of 2019. The Ryfylke tunnel will be both the longest and deepest undersea road tunnel built anywhere in the world when it opens to traffic. The new link connects the city of Stavanger with Strand in the district of Ryfylke. Two other tunnels form part of the project to build the new Ryfast link. These are the Hundvåg tunnel and the Eiganes tunnel, due to open in February 2020 once finishing and testing works have been completed. The opening of all t
  • Seismic Reinforcement Materials Market exceeding at 4% CAGR to cross $40bn by 2025
    July 10, 2019
    According to a new research report by Global Market Insights, Inc. Seismic Reinforcement Materials Market will surpass USD 40 billion by 2025. Increasing seismic activities across the globe resulting in loss of life and assets is the prime reason influencing the growth of seismic reinforcement materials market. The products are majorly used in buildings to strengthen the structures in order to minimize damage possibilities during or after earthquakes. Increasing awareness and implementation of various buil
  • US$2.38 billion road works for Tacoma, WA
    December 23, 2024
    A US$2.38 billion road project is planned for Tacoma, WA.