Delays to highway, tunnel and bridge building

The Slovakian government is being asked for financial compensation by Granvia, the group building the country’s new Nitra-Banska Bystrica highway. Granvia is building the highway under the PPP model through a 30-year concession deal. The compensation has been requested due to delays that have been caused by the need for archaeological investigations along the route.
May 14, 2012 Read time: 2 mins
The Slovakian government is being asked for financial compensation by 5822 Granvia, the group building the country’s new Nitra-Banska Bystrica highway.

Granvia is building the highway under the PPP model through a 30-year concession deal. The compensation has been requested due to delays that have been caused by the need for archaeological investigations along the route.

The highway had been due to be opened in stages from September 2011 to mid 2012 but the schedule is likely to be delayed due to the need for the archaeological work. Adjudicators are evaluating the need for any compensation. The project is costing some €1.8 billion for its construction and the whole deal is worth €3.8 billion over the 30-year concession.

And work is underway on four sections of Slovakia’s D1 highway. Consortium Zilinska Dialnica is building these stretches of highway under a 30-year concession model in a deal worth some e8.55 billion.

The D1 highway is being built under the PPP model and the 30.7km Zilina-Martin stretch is costing €4.2 billion. Funding for the 75km stretch from Dubna Skala towards Kosice is still being finalised. The project is being carried out by concession company Žilinská Dial’nica, which is formed of 981 Hochtief, 1332 Alpine Bau and 1340 FCC Construcción. The concession partners will build 25km of highway as well as 6km of access roads and the work includes 10.6km of tunnels and 7.6km of bridges.


For more information on companies in this article

Related Content

  • Champlain Bridge set to open by end of year, says SNC-Lavalin
    March 6, 2018
    The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
  • NDS to spend US$2.21bn on Zilina, Slovakia motorways
    July 1, 2013
    NDS, the Slovak national motorway company, plans to spend US$2.21 billion (€1.7bn) between 2013 and 2016 on motorway construction projects in the Zilina region of Slovakia. Milan Gajdos, the firm’s managing director and chairman, said that post 2016 a further $1.04 billion (€800mn) will be invested in the region. Currently, tenders worth $1.82 billion (€1.4bn) for motorway projects in the region are already underway, including tenders for stretches of the D1 and D3 motorways. It is still not known whether t
  • New international trade crossing linking Canada and US
    June 9, 2015
    The Detroit River is short, only 45km, and narrow in places, less than 1km. Around a quarter of the annual $658 billion Canada-US trade crosses over the river. That’s $160 billion worth of goods trucked each year between Detroit in the US state of Michigan and the Canadian city of Windsor in the province of Ontario - the Windsor-Detroit Corridor. There are several types of crossings, but the vast majority of commercial traffic must use the 2.3km Ambassador Bridge (see box). A new bridge was initially prop
  • Mountain View Partners to start on Calgary’s Southwest Ring Road
    July 19, 2016
    Preliminary utilities work is set to begin in September on the last section a ring road around the Canadian city of Calgary. The Calgary Herald newspaper quoted the Alberta provincial infrastructure and transportation minister Brian Mason saying that the project is on schedule. He said “everything is going as planned … It’s important that we keep on top of this and it’s important that we keep it moving forward and so far we’re doing just that.” The public-private-partnership project for the southwest