Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • New Russian bridge link spanning Vistula
    November 4, 2020
    A new Russian bridge link is planned spanning the Vistula Lagoon.
  • Tunnels and bridges, improving Argentina's major road link
    May 2, 2012
    A road improvement plus tunnel and bridge building contract in an area once inhabited by dinosaurs in northern Argentina, is a small but key part of an ambitious project to complete a road that will eventually link the Atlantic and Pacific coasts of Latin America - Adriana Potts reports. Remote, rough and spectacular are words that come to mind when describing the mountains of Ischigualasto in Argentina's northern province of San Juan This is the only place in the world where an undisturbed sequence of rock
  • Cross Fraser Partnership wins BC tunnel work
    September 27, 2024
    The partnership for the tunnel work near Vancouver in Canada consists of Pomerleau BC, Bouygues Construction Canada and Fomento de Construcciones y Contratas Canada (FCC) and is supported by design and engineering consultant Arcadis.
  • Webuild proposes Baltimore Bridge design
    May 6, 2024
    VIDEO: The project in the US state of Maryland to replace the collapsed Francis Scott Key Bridge was made free of charge ahead of tomorrow’s state-led virtual industry forum for reconstruction of the bridge.