Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Parsons wins Kentucky interchange deal
    December 1, 2017
    A team of specialists from Parsons is now commencing work on developing a series of options for the I-265/I-64 Interchange project in Kentucky.
  • Long-lasting surface repairs for Avonmouth Bridge
    July 9, 2012
    Two technologies combined to give a heavily used bridge a new surface that should last for years The Avonmouth Bridge carries the M5 motorway over the River Avon, and is a vital part of the road infrastructure in south-west England, linking the counties of Somerset, Devon and Cornwall to the rest of the country. Completed in 1973, it carries commuters to the city of Bristol, and to South Wales, along with holidaymakers. The 1.4km long steel box girder bridge comprising a 16,000m2 steel decked central span a
  • Bosphorus crossing updates
    November 29, 2013
    A group of seven banks is to fund the construction of the third Bosphorus Bridge crossing in Turkish commercial centre Istanbul. A group of six Turkish banks, Garanti Bankasi, Halk Bankasi, Is Bankasi, Vakiflar Bankasi, Ziraat Bankasi, and Yapi Kredi Bankasi, is being joined by the Netherlands-based Garantibank International to provide the necessary US$2.3 billion of funding required for the project. A joint Italian-Turkish consortium comprising Astaldi and IC Ictas will build the bridge, which will reduce
  • Turkey’s Bosporus bridge opening
    August 25, 2016
    Turkey’s Yavuz Sultan Selim Bridge over the Bosporus is having its official opening, which is being carried out by senior members of the country’s government including president Recep Erdoğan. The final sections of the deck structure were put into place in March 2016 and the project, which commenced in 2013, has been completed in record time. This is the third bridge to span the Bosporus at Turkey’s commercial centre, Istanbul and the new crossing will form part of the country’s North Marmara Highway pro