Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Colombia road project tender process
    July 22, 2019
    The tender process for Colombia’s Buga-Buenaventura fourth generation (4G) toll road project is being planned. The tender for the 114.1km dual carriageway is being handled in two separate stretches however. One of the road stretches will be for a 55.4km section from Buga to Loboguerrero, which is expected to cost US$359.45 million. The 58.7km stretch from Loboguerrero to Buenaventura meanwhile is expected to cost $362.75 million. The Loboguerrero to Buenaventura section of the route includes building a 19km
  • Work starting on second Chesapeake Tunnel project
    September 20, 2017
    Work is now starting on a major tunnel project in the US state of Virginia. Construction of a second tunnel connection for the Chesapeake Bay is expected to cost US$756million. The original Chesapeake Bay Tunnel and Bridge crossing opened to traffic in April 1964 and measures just over 37km long. Construction of a second parallel bridge was commenced in 1995 and opened to traffic in 1999. However the central tunnel link was not widened at that time and now carries more traffic than it was designed for, whil
  • Bulgarian highway faces construction delays
    September 24, 2014
    In Bulgaria questions hang over the construction of a section of the Struma Highway. Greek construction company Aktor was originally awarded the contract for Lot 4 of the Struma Highway but work on the project slipped behind schedule. The delays seen so far with the project have not been well received within the Bulgarian Government. The work was supposed to have been completed around the end of 2014 or the beginning of 2015 and the country’s transport ministry has said that work on the highway cannot be de
  • Chilean deal
    February 6, 2012
    Skanska is preferred bidder to develop the Antofagasta Toll Road in Chile under a PPP model. The firm has beaten tough competition for this project and says it will not require government subsidies for the work, which is due to commence in 2011.