Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Additional Argentina-Chile tunnel project proposed
    January 9, 2015
    An agreement has been reached between Chile and Argentina over a long discussed tunnel project. The proposed tunnel would stretch 11.5km and connect Argentina’s Mendoza Province with Chile’s Region VI, with the project having first been mooted as far back as 1992. The cost of the proposed Paso Las Lenas Tunnel has yet to be revealed although the projected route through the Andes Mountains has been announced. The tunnel portals will be some 2,050m above sea level and the project will include the construction
  • Norway's bridge meets tough environmental targets
    May 2, 2012
    One of the world's longest bridges is being built in Norway – for traffic volumes of just 2,000 cars/day reports Adrian Greeman. The stunning landscape of the long sea fjords in Norway is one of its glories, attracting thousands of tourists every summer. But the high mountains and deep sea inlets are also one of the great obstacles to transport and development.
  • Norway's bridge meets tough environmental targets
    February 27, 2012
    One of the world's longest bridges is being built in Norway – for traffic volumes of just 2,000 cars/day reports Adrian Greeman. The stunning landscape of the long sea fjords in Norway is one of its glories, attracting thousands of tourists every summer. But the high mountains and deep sea inlets are also one of the great obstacles to transport and development.
  • New Chile-Argentina tunnel project to open for bids
    April 19, 2016
    The bidding process for the Agua Negra Tunnel project that will link Chile with Argentina looks set to commence in July or August 2016. The bidding is being organised jointly by the governments of both Chile and Argentina. One source of funding for the project is also now secured, with a loan of US$1.5 billion being provided by the Inter-American Development Bank (IADB). In addition the IADB has also approved $20 million in funding for Chile and Argentina to finance the project's environmental impact studie